- Overview
- Construction Cameras
- Construction Activities
- Photos
- Project Updates
- Public Documents
- Public Meetings
- Social Media
- Events
Project Overview
| Contractor | Griffith Company |
| Construction Start | April 2012 |
| Construction Completion | Fall 2013 |
| Project Helpline | (877) 672-7765 |
Project Improvements
- Widen Clinton Keith Road
- Widen on and off-ramps
- Add ramp meters to on-ramps
- Add HOV lanes to on-ramps
Click map to zoom in
Construction Cameras
Camera 1 (Looking west from south-east corner of interchange)
Camera 2 (Looking north from south of interchange)
Construction Activities
May 6, 2013
Lane & Off-ramp closures on I-15 at Clinton Keith Interchange. May 6 – 10th. Please click here for details: CKNOWMay6
April 8, 2013
Clinton Keith Road Interchange Lane & Off-ramp closures scheduled for April 8-15 , click here for the Notice of Work with more details.
March 21, 2013
Over the next 10 days, dirt will be hauled in to the job site by numerous trucks between the hours of 7:00 a.m. and 3:30 p.m. Please see the following map which shows the haul route.
March 15, 2013
The following lane and ramp closures will be performed on I-15 at Clinton Keith Rd. The purpose of the closures is to allow for concrete paving.
Southbound Lane Closures March 18 to the 19
8:00 pm to 6 am Lane #3
10:00 pm to 5 am Lane #2
8:00 pm to 6 am On/Off Ramp The north and south bound ramps will not be closed at the same time.
Northbound Lane Closures March 18 to the 19
8:00 pm to 6 am Lane #3
10:00 pm to 5 am Lane #2
8:00 pm to 6 am On/Off Ramp (The north and south bound ramps will not be closed at the same time.)
Southbound Lane Closures March 19 to the 20
8:00 pm to 6 am Lane #3
10:00 pm to 5 am Lane #2
8:00 pm to 6 am On/Off Ramp (The north and south bound ramps will not be closed at the same time.)
Northbound Lane Closures March 19 to the 20
8:00 pm to 6 am Lane #3
10:00 pm to 5 am Lane #2
8:00 pm to 6 am On/Off Ramp (The north and south bound ramps will not be closed at the same time.)
Southbound Lane Closures March 20 to the 21
8:00 pm to 6 am Lane #3
10:00 pm to 5 am Lane #2
8:00 pm to 6 am On/Off Ramp (The north and south bound ramps will not be closed at the same time.)
Northbound Lane Closures March 20 to the 21
8:00 pm to 6 am Lane #3
10:00 pm to 5 am Lane #2
8:00 pm to 6 am On/Off Ramp (The north and south bound ramps will not be closed at the same time.)
March 8, 2013
Traffic Signals Shut Down on Clinton Keith Road at Hidden Springs Road
When: Thursday, March 14, 2013 from 9am – to 3pm
The purpose of shutting down the signal is to allow for the installation of a new signal pole. No detour is necessary. Please expect delays.
March 4, 2013
Clinton Keith Road Interchange Lane & Off-ramp closures scheduled for March 4-9 , click here for Notice of Work with more details.
February 25, 2013
Clinton Keith Road Interchange Lane & Off-ramp closures scheduled for February 27-28, click here for Notice of Work with more details.
Traffic signal light shutdown scheduled for February 27th at the Southbound Ramp Intersection, between 9am-3pm, click here for Notice of Work with more details.
February 4, 2013
Full Freeway Closure on I-15 at Clinton Keith Road from February 4-7, 2013
The following closures will be performed in order to allow for bridge demolition. Please see detours below. Click here for PDF Notice of Work.
| Date | Closure |
| February 4, 2013 10:00 PM – 4:00 AM |
Southbound I-15 at Clinton Keith |
| February 5, 2013 10:00 PM – 4:00 AM |
Southbound I-15 at Clinton Keith |
| February 6, 2013 10:00 PM – 4:00 AM |
Southbound I-15 at Clinton Keith |
| February 5, 2013 11:00 PM – 5:00 AM |
Northbound I-15 at Clinton Keith |
| February 6, 2013 11:00 PM – 5:00 AM |
Northbound I-15 at Clinton Keith |
| February 7, 2013 11:00 PM – 5:00 AM |
Northbound I-15 at Clinton Keith |
Detours
|
Where |
Detour |
| Northbound I-15 |
Traffic will be directed off the freeway at Clinton Keith and back on via the northbound on-ramp. |
| Southbound I-15 |
Traffic will be directed off the freeway at Clinton Keith and back on via the southbound on-ramp. |
| Northbound I-15 to Clinton Keith Rd west of I-15 |
Traffic will be directed off the freeway at Clinton Keith and back on via the northbound on-ramp. Exit at Baxter Road, make a left and enter southbound I-15. Exit at Clinton Keith and go west. |
| Southbound I-15 to Clinton Keith Rd east of I-15 |
Traffic will be directed off the freeway at Clinton Keith and back on via the southbound on-ramp. Exit at California Oaks Road, make a left and enter northbound I-15. Exit at Clinton Keith and go east. |
| Westbound Clinton Keith Road to Clinton Keith Road west of I-15 | Enter northbound I-15 on-ramp. Exit at Baxter Road, make a left and enter at Clinton Keith and go west. |
| Eastbound Clinton Keith Road to Clinton Keith Road east of I-15 | Enter southbound I-15 on-ramp. Exit at California Oaks Road, make a left and enter northbound I-15. Exit at Clinton Keith and go east. |
November 26, 2012
Traffic signal shuts down on Clinton Keith
Construction crews will be shutting down various traffic signals along Clinton Keith Road to allow for electrical work to be performed. Please see the schedule below:
Tuesday, Nov 27 from 9 AM – 3 PM
Hidden Springs and Clinton Keith
Wednesday, Nov 28 from 9 AM – 3 PM
Ayra Drive and Clinton Keith
Thursday, Nov 29 from 9 AM – 3 PM
Ayra Drive and Clinton Keith
Hidden Springs and Clinton Keith
November 16, 2012
Full freeway closure on I-15 at Clinton Keith Rd.
On Monday, November 19, there will be a full freeway closure on I-15 at Clinton Keith Rd to allow construction crews to pour concrete on the bridge.
Southbound Closure – 10 p.m. – 1 a.m.
Northbound closure – 1 a.m. – 5 a.m.
Detours
Northbound I-15
Traffic will be directed off the freeway at Clinton Keith and back on via the northbound on-ramp.
Southbound I-15
Traffic will be directed off the freeway at Clinton Keith and back on via the southbound on-ramp.
Northbound I-15 to Clinton Keith Road west of I-15
Traffic will be directed off the freeway at Clinton Keith and back on via the northbound on-ramp. Exit at Baxter Road, make a left and enter southbound I-15. Exit at Clinton Keith and go west.
Southbound I-15 to Clinton Keith Road east of I-15
Traffic will be directed off the freeway at Clinton Keith and back on via the southbound on-ramp. Exit at California Oaks Road, make a left and enter northbound I-15. Exit at Clinton Keith and go east.
Westbound Clinton Keith Road to Clinton Keith Road west of I-15
Enter northbound I-15 on-ramp. Exit at Baxter Road, make a left and enter at Clinton Keith and go west.
Eastbound Clinton Keith Road to Clinton Keith Road east of I-15
Enter southbound I-15 on-ramp. Exit at California Oaks Road, make a left and enter northbound I-15. Exit at Clinton Keith and go east.
November 6, 2012
Northbound & Southbound off ramp closures at I-15 Clinton Keith Interchange
Tuesday, November 6 –Thursday, November 8, 2012
November 6, 2012 N/B 8 p.m. – 6 a.m.
November 7, 2012 S/B 8 p.m.- 6 a.m.
November 8, 2012 N/B 8 p.m. – 6 a.m. CANCELLED
October 19, 2012
Full Freeway Closure on I-15 at Clinton Keith Road from October 22 to October 26
The following closures will be performed in order to allow the contractor to install falsework at the Clinton Keith overcrossing. Please see detours below.
| Date | Closure |
| October 22, 2012 10:00 PM – 4:00 AM |
Southbound I-15 at Clinton Keith and the overcrossing. |
| October 23, 2012 11:00 PM – 5:00 AM |
Northbound I-15 at Clinton Keith and the overcrossing |
| October 24, 2012 10:00 PM – 4:00 AM |
Southbound I-15 at Clinton Keith and the overcrossing. |
| October 25, 2012 11:00 PM – 5:00 AM |
Northbound I-15 at Clinton Keith and the overcrossing |
| October 26, 2012 11:00 PM – 4:00 AM |
Southbound I-15 at Clinton Keith and the overcrossing. |
Detours
DetNorthbound I-15 Closure Detour – click map to zoom in
Southbound I-15 Closure Detour – click map to zoom in
October 3, 2012
Lane Closures at Clinton Keith Interchange
The following closures will be performed in order to allow the contractor to pour concrete at the Clinton Keith interchange. There is no detour necessary.
| Date | Closure |
| Monday, October 8, 2012 9:00 PM – 6:00 AM |
Inside 2 lanes Southbound I-15 at Clinton Keith interchange |
| Tuesday, October 9, 2012 9:00 PM – 6:00 AM |
Inside 2 lanes Northbound I-15 at Clinton Keith interchange |
September 19, 2012
On the night of Monday, September 24, 2012, construction crews will perform lane closures on I-15 at Clinton Keith Rd. The closures will occur during the following hours:
Northbound I-15 (inside 2 lanes) – 9 p.m. – 6 a.m.
Southbound I-15 (inside 2 lanes) – 9 p.m. – 6 a.m.
The purpose of these lane closures is to allow crews to pour concrete. No detour is necessary. Please expect minor traffic delays.
August 30, 2012
Lane Closures at Clinton Keith Interchange
The following closures will be performed in order to allow the contractor to pour concrete at the Clinton Keith interchange. Please see detours below.
| Date | Closure |
| Wednesday, Sept 5, 2012 9:00 PM – 6:00 AM |
Inside 2 lanes Southbound I-15 at Clinton Keith interchange |
| Wednesday, Sept 5, 2012 9:00 PM – 6:00 AM |
Inside 2 lanes Northbound I-15 at Clinton Keith interchange |
July 31, 2012
Full Freeway Closures on I-15 at Clinton Keith Interchange from August 6 – 9
The following closures will be performed in order to allow the contractor to install falsework at the Clinton Keith overcrossing. Please see detours below.
| Date | Closure |
| Monday, Aug 6, 2012 10:00 PM – 4:00 AM |
Southbound I-15 at Clinton Keith and the overcrossing. |
| Tuesday, Aug 7, 2012 11:00 PM – 5:00 AM |
Northbound I-15 at Clinton Keith and the overcrossing |
|
CLOSURES BELOW HAVE BEEN CANCELED |
|
| Wednesday, Aug 8, 2012 10:00 PM – 4:00 AM |
Southbound I-15 at Clinton Keith and the overcrossing |
| Thursday, Aug 9, 2012 11:00 PM – 5:00 AM |
Northbound I-15 at Clinton Keith and the overcrossing |
Detours
Northbound I-15 Closure Detour – click map to zoom in
Southbound I-15 Closure Detour – click map to zoom in
7/23/2012
Full Freeway Closures on I-15 at Clinton Keith Interchange
The following closures will be performed in order to allow the contractor to install falsework at the Clinton Keith overcrossing. Please see detours below.
| Date | Closure |
| Wednesday, July 25, 2012 10:00 PM – 4:00 AM |
Southbound I-15 at Clinton Keith and the overcrossing. |
| Thursday, July 26, 2012 11:00 PM – 5:00 AM |
Northbound I-15 at Clinton Keith and the overcrossing |
| Friday, July 27, 2012 11:00 PM – 4:00 AM |
Southbound I-15 at Clinton Keith and the overcrossing |
| Monday, July 30, 2012 11:00 PM – 5:00 AM |
Northbound I-15 at Clinton Keith and the overcrossing |
| Tuesday, July 31, 2012 10:00 PM – 4:00 AM |
Southbound I-15 at Clinton Keith and the overcrossing |
Detours
Northbound I-15 Closure Detour – click map to zoom in
Southbound I-15 Closure Detour – click map to zoom in
6/13/2012
Full freeway closures for Wednesday and Thursday night have been canceled
Construction crews completed the demolition of the north side of the Clinton Keith overcrossing ahead of schedule. The full freeway and overcrossing closures originally scheduled for Wednesday and Thursday night have been canceled as they are no longer necessary.
6/5/2012
Full Freeway Closures on I-15 at Clinton Keith Interchange
The following closures will be performed in order to allow the contractor to demo the barrier on the north side of the Clinton Keith overcrossing. Please see detours below.
| Date | Closure |
| Monday, June 11, 2012 11:00 PM – 4:00 AM |
Northbound I-15 at Clinton Keith and the overcrossing. |
| Tuesday, June 12, 2012 10:00 PM – 3:00 AM |
Southbound I-15 at Clinton Keith and the overcrossing |
| Wednesday, June 13, 2012 11:00 PM – 4:00 AM |
Northbound I-15 at Clinton Keith and the overcrossing |
| Thursday, June 14, 2012 10:00 PM – 3:00 AM |
Southbound I-15 at Clinton Keith and the overcrossing |
Detours
Northbound I-15 Closure Detour – click map to zoom in
Southbound I-15 Closure Detour – click map to zoom in
Project Updates
I-15 / Clinton Keith Groundbreaking Event
It was a morning that some local elected officials and residents thought would never take place. On Friday, March 30, 2012 with a foggy early morning sky which introduced a beautiful sun-filled afternoon, Groundbreaking ceremonies were held, initiating the I-15/Clinton Keith Widening Project in the City of Wildomar.
This event was well attended by officials from the Riverside County Transportation Department, California Department of Transportation, Western Riverside Council of Governments, Wildomar Mayor, Ben Benoit, Riverside County Supervisor, Bob Buster, and almost 90 other guests. The event was the commencement of a $13.47 million dollar project that will significantly improve congestion and enhance safety.
The planned improvements of reconstructing Clinton Keith at the I-15 interchange include widening Clinton Keith Road (in the vicinity of I-15), overcrossing to three lanes in each direction, the addition of auxiliary lanes on I-15, drainage, lighting, sign improvements, ramp metering on both on-ramps, and signal modifications.
Funding is provided by a combination of sources: Transportation Uniform Mitigation Fund (TUMF), Developer Impact Fees – Southwest Area, Southwest Area Road and Bridge Benefit District, and City of Murrieta Funds.
Officials estimate that more than 250 jobs will be created over the next two years as a direct and indirect result of the construction process. Construction began in April 2012, the project duration is 18-24 months and is expected to be completed by Winter, 2013.
Public Documents
To save file on your computer:
PC – Right-click on link, select “Save link as”
Mac – Ctrl-click on link, select “Download”
| Name | Posted Date | File Type |
|---|---|---|
| Ramp Closure Notice & Detour Map | April 9, 2013 | |
| Notice of Work | April 8, 2013 | |
| Notice of Work | January 14, 2013 | |
| Notice of Work | May 10, 2012 | |
| Notice of Work | May 2, 2012 | |
| Notice of Work | May 1, 2012 | |
| Notice of Work – Update | April 18, 2012 | |
| Notice of Work | April 11, 2012 | |
| Press Release – Community Meeting | March 21, 2012 | MS Word |
| Project Information Handout | February 2012 | |
|
|
Public Meetings
Monthly Meetings
| Title | Date / Time | Location |
|---|---|---|
| Community Information Meeting |
Future meetings will be scheduled as needed |
Wildomar City Hall |
| Business Coordination Meeting | Future meetings will be scheduled as needed |
Wildomar City Hall |
Events
| Title | Date / Time | Location |
|---|---|---|
| Clinton Keith Groundbreaking | March 30, 2012 10:00 AM |
Behind USA Gas |






