Jefferson St. Update for August 5

All work on the interchange has moved to night-work due to extreme heat conditions during the daytime.  The Contactor has a minimal work force during the daytime hours.  This work schedule is expected to continue through the end of summer.

IMG_5995

Stem forms being constructed in the right bridge. This is the north end of the bridge.

IMG_5998

Progress of the stem form construction looking south.

IMG_5999

MSE wall construction at the southeast corner of the bridge.

IMG_6001

Dirt backfill at the south end of the bridge.