Upcoming Ramp Closures on I-10 at Jefferson St. June 19 – 23

Ramp closures will take place on I-10 at Jefferson Street June 12 – 16. The purpose of these closures is to  continue bridge and roadway construction activities.

Closure Schedule

EB on-ramp day:

Monday through Friday, June 19 – 23, 2017. 5:00 AM – 5:00 PM

EB on-ramp night:

Nights of Monday through Friday, June 19 – 23, 2017. 7:00 PM – 7:00 AM

WB off-ramp day:

Monday through Friday, June 19 – 23, 2017. 5:00 AM – 5:00 PM

WB loop on-ramp day:

Monday through Friday, June 19 – 23, 2017. 5:00 AM – 5:00 PM

Detour for closure of EB I-10 On-ramp at Jefferson St.

  1. Go east on Varner Rd. to Monroe St.
  2. Turn right at Monroe St.
  3. Turn left at the EB I-10 on-ramp.

EB on-ramp closure detour v4

Detour for closure of WB I-10 Off-ramp at Jefferson St.

  1. Exit at Monroe St. and turn right.
  2. Turn left at Varner Rd./Ave. 42.

WB off-ramp closure detour v4

Detour for closure of WB I-10 Loop On-ramp at Jefferson St.

  1. Continue on Indio Blvd. north.
  2. Turn left at Varner Rd.
  3. Turn left at Jefferson St. south.
  4. Turn right at the WB I-10 on-ramp.