Newport Road Construction Activities for July 20-24

Ramp and Bridge Construction

Please see the schedule below for next week’s anticipated closures.

 
July 20-24
Monday-Friday     
8pm-5am
Intermittent freeway lane closures southbound I-215
between Scott Road and McCall Boulevard^Intermittent ramp closures southbound I-215 on- and off-ramps
July 20-24
Monday-Friday
10pm-5am
Intermittent freeway lane closures northbound I-215
between Scott Road and McCall Boulevard^Intermittent ramp closures northbound I-215 on- and off-ramps
   
 ^ At least one lane in each direction will be open at all times.
* There are two on-ramps and two off-ramps on Newport Road. There will always be one on-ramp and one off-ramp open at all times.
 
 map720

Upcoming Lane Reductions on Newport Road

Please be advised that construction work on Newport Road for median removal is scheduled to start at the end of July, and is anticipated to be completed within 2-3 weeks. Lanes will temporarily be reduced to two lanes in each direction during this period.

 

Upcoming Full Freeway Closures on I-215/Newport Road

Crews are scheduled to work on the bridge falsework on July 27-31, Monday-Friday from 10pm to 5am. Mainline traffic will be diverted to use the off- and on-ramps at Newport Road as temporary detours during these night closures. More detour information will be made available to the public.

 

Click here to view the printable PDF.

 

Please plan ahead in anticipation of the temporary increased traffic in this area. If possible, please avoid the project corridor and use an alternate route.

Motorists and pedestrians should slow down and use caution when traveling through work zones, near barricades and equipment.