| Contractor | All American Asphalt |
| Construction Start | February 2012 |
| Construction Completion | late March 2013 |
| Work Hours | Monday – Friday 7 AM – 6 PM Some weekend work, which includes occasional ramp and road closures, is anticipated. |
| Project Helpline | (877) 221-1472 |
Project Improvements
- Widen Indian Truck Trail to four lanes with dedicated left and right-turn lanes from just west of the interchange to Temescal Canyon Road.
- Install a sidewalk on the south side of Indian Truck Trail.
- Construct walls under the I-15 bridges.
- Add three new traffic signals at the SB and NB I-15 / Indian Truck Trail ramp intersections, and at the intersection of Indian Truck Trail / Temescal Canyon Road.
- Add ramp meters on I-15 NB and SB on-ramps.
- Reconfigure and construct the intersection of Indian Truck Trail and Temescal Canyon Road.
Construction Activities
March 12, 2013
NB I/15 8 p.m. to 4 a.m.
SB I/15 11 p.m. to 6 a.m.
March 13, 2013
NB I/15 8 p.m. to 4 a.m.
SB I/15 11 p.m. to 6 a.m.
March 14,2013
NB I/15 9 p.m. to 4 a.m.
SB I/15 11p.m. to 6 a.m.
March 15, 2013
NB I/15 10 p.m. to 6 a.m.
Friday Morning, March 16 at 12:01 a.m.
SB I/15 12:01 a.m. to 7 a.m.
March 11, thru March 14, 2013
NB on and off ramps 8 p.m. to 4 a.m.
SB on and off ramps 9 p.m. to 5 a.m.
March 15, 2013
NB on and off ramps 10 p.m. to 6 a.m.
SB on and off ramps 11 p.m. to 6 a.m.
WHY: Traffic loop installation and striping
DETOUR:
Off-ramp closures
Northbound I- 15
Option 1
Exit at Lake Street, left on Lake Street, right to Temescal Canyon Road, left to Indian Truck Trail
Option 2
Exit at Lake Street, left on Lake Street, right to Temescal Canyon Road, left to Horse Thief Canyon Road, right to De Palma Road to Indian Truck Trail
Southbound I-15
Option 1- Exit on Temescal Canyon Road, right on Campbell Ranch Road to Indian Truck Trail
Option 2- Exit on Temescal Canyon Road to Indian Truck Trail
On – ramp closures
Northbound I- 15
Option 1- Follow detour from Temescal Canyon Road to Temescal Canyon Road on-ramp
Option 2- Follow detour from Campbell Ranch Road to Temescal Canyon Road to Temescal Canyon Road on-ramp.
Southbound I-15
Option 1- Follow detour from De Palma Road, left to Horse Thief Road, right to to Temescal Canyon Road and left to Lake Street to the Lake Street on-ramp
Option 2- Follow detour from Temescal Canyon Road, left to Lake Street to the Lake Street on-ramp
CONTACT: Dennis Green, 909.800.0451 (cell)
Northbound on/off ramp 8:00 p.m. – 4:00 a.m.
Southbound on/off ramp 9:00 p.m. – 5:00 a.m.
Click Here for more details including detours.
Northbound off- ramp 10:00 p.m. – 4:00 a.m.
Southbound off- ramp 11:00 p.m. – 5:00 a.m.
Indian Truck Trail Ramp Closure
When: January 22 – January 24
Northbound on/off ramps 8:00pm – 4:00am
Southbound on/off ramps 9:00pm – 5:00am
Where: Temescal Valley: Indian Truck Trail Road
Wednesday 12/19/12: prime coat cure
Thursday 12/20/12 at 07:00: pave HMA-A, install traffic control then open the ramp for traffic as scheduled at 21:00 (09:00 PM),
12/11/2012
UPDATED: Indian Truck Trail Ramp Closures Beginning Nov 26
Construction crews will be performing closures on the I-15 on and off-ramps at Indian Truck Trail beginning November 26. These closures are part of the Indian Truck Trail Interchange Project. Please click the links below for details.
Ramp Closure Details (English)
Ramp Closure Details (Spanish)
8/30/12
Temescal Canyon Road is NOW OPEN.
Northbound Temescal Canyon Road Closure
Northbound Temescal Canyon Road will be closed July 20, 2012 through late September 2012. The Closures will include the Intersection at Temescal Canyon Rd and Indian Truck Trail and Northbound Temescal Canyon Rd between Corona Lake entrance and Campbell Ranch Rd. Click on the maps below for detour information.