Leon Road Roadway Safety Improvements

Keller Road to Scott Road

Project Overview

Estimated Project Cost $1,245,000

Leon 2-8-07 083 hill sign 

Construction Start April 2013
Construction Duration 5 months
Cooperating Agencies

Riverside County Transportation 
City of Menifee

Project Contact Dennis Green , (909) 887-6056

 

Project Improvements

The County of Riverside and City of Menifee are working together to improve driving conditions on Leon Road.  The existing asphalt will be removed and replaced from Keller Road to south of Scott Road.  Grading will lower the high spots and fill in the large dips on Leon Road.  This will greatly improve sight distance and traffic safety.  As an additional safety feature, four-foot paved shoulders will be added.

The project will begin with construction of a retaining wall on the east side of Leon Road, between Via Las Rosas and Fowler Drive.  After the retaining wall is complete, the road reconstruction will begin.  The total project is expected to last approx. 3 months.

The project construction cost is estimated at $1,245,000.  Major funding for this project is provided by the Highway Safety Improvement Program (HSIP) for which the County successfully competed for.

Leon 2-8-07 090 Car peeks over hill

Car peeks over hill

Leon 2-8-07 088 truck in dip

Truck heads toward dip

 

 

Construction Schedule

When
Description
Accessibility 
April 2013 Construct retaining wall Road will remain open
June 5, 2013 

Road closed for 6 weeks between Keller Rd & Scott Rd, beginning June 5, 2013 until August 5th, 2013.
Click here for DETOUR MAP: Leon Rd Detour Map 

 

Detour:  Northbound – Jean Nicholas to SR79 to Scott Rd
Southbound – Scott Rd to SR79 to Jean Nicholas
Local residents will be allowed access. 

Leon Rd detour map

 

August 2013 Construction complete in early August  

Construction Details

Construction Hours 7:00 AM to 6:00 PM
Work Days Monday to Friday
Local Residents Access passes will be available
Deliveries/Services

The contractor will work with the Post Office, FedEx, trash pickup, etc. to avoid disruption of services

Project Contact Dennis Green , (909) 887-6056

Public Documents

Name Description PDF Link
Notice of Work Leon Road – Keller Rd to Scott Rd now through August 5, 2013  Notice of Work – July 8
Detour Map Detour Map for 6-week Leon Road Closure beginning June 5, 2013 Leon Rd Detour Map
Notice of Work  Notice of Work, June 5, 2013.  6 Week Road Closure.  Leon Road Notice of Work
     

Project Contacts

Dennis Green, Green Com, Inc.
(909) 887-6056