We are continuing with the pavement rehabilitation project to Johnston Avenue from San Jacinto Street to Stanford Street in the East Hemet area. Contractor is working on asphalt dike along the road and preparing for the installation of traffic stripe and pavement markings. Please use caution and observe construction warning signs while travelling through the work areas. Thank you for your patience and understanding!
The contractor is continuing with hauling debris to disposal sites and cleaning up the areas (weather permitting). The road/bridge is no longer accessible for traffic as well as pedestrians. Please DO NOT ENTER the demolished area.
Clinton Keith Road connecting Leon Road and Winchester Road (SR 79) in the French Valley/City of Murrieta is OPEN. The contractor is continuing with the construction to complete contract work and improvements. Please continue to use caution and observe construction warning signs. Thank you for your patience and understanding!
We completed with the pavement rehabilitation to Johnston Avenue from San Jacinto Street to Stanford Street in the East Hemet area. Due to recent rain events and forecasted rain, no construction work scheduled for next week. Please continue to use caution and observe construction warning signs while travelling through the work areas. Thank you for your patience and understanding!
Clinton Keith Road connecting Leon Road and Winchester Road (SR 79) in the French Valley/City of Murrieta is OPEN. The contractor is continuing with the construction to complete contract work and improvements. Please continue to use caution and observe construction warning signs. Thank you for your patience and understanding!
DAYTIME ROAD CLOSURE: TRAFFIC IMPACTS
Detroit Street will be closed to through traffic at Hamner Avenue during daytime work.
Tuesday - Thursday
Feb. 6 -8
9 a.m. to 3 p.m.
Use alternate routes, add extra time for travel, and follow detour for local access.
PROJECT REMINDER:
REDUCE SPEED to 35 mph in the project area, watch for crews working on the shoulder from Detroit to Citrus streets, along the length of the bridge, and in the center median from Alhambra to Detroit streets.
NO PEDESTRIAN ACCESS across the bridge
USE @RiversideTransitAgency ROUTE 3
Check out RTA’s website for more information https://www.riversidetransit.com/
Route 3:
https://www.riversidetransit.com/.../Route%203%20%7C...
SUBSCRIBE at http://www.hamneraveproject.com/updates/
STAY CONNECTED on IG @hamneraveproject and on FB @Hamner Avenue Bridge and Widening Project.
JURUPA ROAD GRADE SEPARATION Project ROAD CLOSURE EXTENDED through February 13 due to weather.
We removed 100% of Whitewater Cutoff Bridge. The contractor is continuing with hauling debris to disposal sites and clean up the areas. The road/bridge is no longer accessible for traffic as well as pedestrians. Please DO NOT ENTER the demolished area.
We removed 100% of Whitewater Cutoff Bridge. The contractor is continuing with hauling debris to disposal sites and clean up the areas. The road/bridge is no longer accessible for traffic as well as pedestrians. Please DO NOT ENTER the demolish area.
We are continuing with the pavement rehabilitation project to Johnston Avenue from San Jacinto Street to Stanford Street in the East Hemet area. The contractor is scheduled to finish the final asphalt surface from Columbia Street to San Jacinto Street this week (weather permitting). To avoid delays please use alternate routes. Please use caution and observe construction warning signs while travelling through the work areas. Thank you for your patience and understanding!
Clinton Keith Road connecting Leon Road and Winchester Road (SR 79) in the French Valley/City of Murrieta is OPEN. The contractor is continuing with the construction to complete contract work and improvements. Please continue to use caution and observe construction warning signs. Thank you for your patience and understanding!
We are continuing with the pavement rehabilitation project to Johnston Avenue from San Jacinto Street to Stanford Street in the East Hemet area. Contractor completed first layer of new asphalt and is scheduled to pave final layer this week (weather permitting). To avoid delays please use alternate routes. Please use caution and observe construction warning signs while travelling through the work areas. Thank you for your patience and understanding!
Note: The contractor is tentatively scheduled to pave new asphalt this Saturday, 1/27/24.
Johnston Avenue Resurfacing - Weekly Status
We are continuing with the pavement rehabilitation project to Johnston Avenue from San Jacinto Street to Stanford Street (630 Feet easterly) in the East Hemet area until Mid-March 2024. Contractor is schedule to remove existing asphalt pavement and pave new asphalt on Johnston Avenue from Columbia Street to San Jacinto Street. We suggest use of alternate routes. Please use caution and observe construction warning signs while travelling through the work areas. Thank you for your patience and understanding!
#JurupaGradeSeparationProject
Week of January 22 | Semana de 22 de Enero
TRAFFIC IMPACTS | Expect delays
NB VAN BUREN BLVD. Lane closures between Jurupa Connector Rd. and Rutile St.
Mon., Jan. 22 - Fri., Jan. 26 | 9 a.m.- 3 p.m.
RUTILE ST. east of VAN BUREN BLVD. Road/intersection closure through Feb. 2.
FELSPAR ST. at JURUPA RD. Lane closure on Felspar St. through January.
IMPACTOS DEL TRÁFICO | Espere retrasos
NB VAN BUREN BLVD. Cierres de carriles entre Jurupa Connector Rd. y Rutile St. lunes 22 de enero - viernes 26
de enero | 9 a.m.- 3 p.m.
RUTILE ST. al este de VAN BUREN BLVD. Cierre de carreteras/intersecciones hasta el 2 de febrero.
FELSPAR ST. en JURUPA RD. Cierre de carril en Felspar St. hasta enero.
STAY INFORMED | MANTENTE INFORMADO
SUBSCRIBE | SUSCRIBIR https://www.jurupagradeseparation.com/updates/
FOLLOW | SEGUIR
FB @Jurupa Grade Separation Project
IG @jurupagradeseparation
REMINDER | RECORDATORIO Shop local Jurupa Valley!
#ShopJV
#ShopJurupaValley
BUSINESS DIRECTORY | DIRECTORIO DE NEGOCIOS
Check out our and support local businesses in Jurupa Valley.
Consulte nuestro y apoye a las empresas locales en Jurupa Valley.
We removed 100% of Whitewater Cutoff Bridge. The contractor is processing concrete spoils and hauling to disposal site. The road/bridge is no longer accessible for traffic as well as pedestrians. Please DO NOT ENTER the demolition area.