Project Overview
The County of Riverside, in cooperation with the City of Menifee and Caltrans, reconstructed the previous interchange located on Interstate 215 (I-215) at Newport Road in the City of Menifee. The improvements reconstructed the previous diamond interchange into a partial cloverleaf interchange configuration, with northbound and southbound loop on-ramps. The existing bridge was widened to accommodate six through lanes of traffic, deceleration lanes approaching the loop on-ramps, outside shoulders that will be used as bike lanes and a sidewalk on the north side of the bridge. On the mainline freeway, acceleration lanes were added to the direct on-ramps and a deceleration lane was added to the northbound off-ramp. The northbound freeway bridge over Salt Creek was widened to accommodate the northbound on-ramp acceleration lane.
Construction start: April 2015
Construction Completion: Spring 2017