Connecting Our Communities

News

Project News

GILMAN SPRINGS ROAD will be CLOSED to through traffic beginning Saturday, Jan. 4, at 8 p.m.

GILMAN SPRINGS ROAD will be CLOSED to through traffic south of Bridge Street beginning Saturday, Jan. 4, at 8 p.m., and continues for 5 weeks, weather permitting.     

Traffic Impacts  

·         Gilman Springs Road will be closed to through traffic SOUTH of Bridge Street for approximately 1 mile. 

·         Gilman Springs road is open to traffic from Bridge Street to SR 60. 

·         Motorists may detour onto Ramona Expressway to Bridge Street to access Gilman Springs Road north of Bridge Street.  

·         Please plan for delays and use alternate routes. 

The road closure is necessary to complete construction south of Bridge Street. The scope of work includes installing a concrete center median, widening the roadway shoulders, improving drainage, installing a metal beam guardrail along the edge of the roadway, repaving, and restriping the road.  

  

 Work schedules may change due to weather or field conditions.  

   

Crews may work 24 hours per day, 7 days a week. 

   

---------------------------------------------------------------------------------------------------  

GILMAN SPRINGS ROAD estará CERRADA al tráfico al sur de Bridge Street a partir del sábado 4 de enero a las 8 p. m. y continuará durante 5 semanas, si el clima lo permite.    

Impactos del tráfico  

Gilman Springs Road estará cerrada al tráfico AL SUR de Bridge Street durante aproximadamente 1 milla. 

La carretera Gilman Springs está abierta al tráfico desde Bridge Street hasta la SR 60. 

·                     Los automovilistas pueden desviarse hacia Ramona Expressway hacia Bridge Street para acceder a Gilman Springs Road al norte de Bridge Street.  

·                     Planifique los retrasos y utilice una ruta alternativa.   

   

El cierre de la carretera es necesario para completar construcción al sur de Bridge Street. el alcance del trabajo incluye la instalación de un centro de hormigón mediana, ampliando los arcenes de la calzada, mejorar el drenaje, instalar una viga metálica barandilla a lo largo del borde de la carretera, repavimentación y repintado de la vía.  

Los horarios de trabajo pueden cambiar debido al clima o las condiciones del campo.  

Las cuadrillas pueden trabajar las 24 horas del día, los 7 días de la semana.  

Hotline: 877.277.5343  

Linea Directa: 877.277.5343  

   

Website: www.rcproject.org/gilman  

Sitio web: www.rcproject.org/gilman  


Yvette Munozgilmanphase6
Slurry Seal FY24-25 District 1,2,3 - Weekly Status

- Repair/upgrade curb ramp throughout the project to meet ADA standard is completed.

- Weed Abatement in Districts 1,2 and 3 is completed.

- Type I and II slurry seal in the Woodcrest area is completed.

- Type I and Type II MSE in the Temescal Valley area is completed.

- Pavement Markings and the Second coat of striping in the Murrieta Hot Springs has been completed.

- Asphalt repairs throughout the project have been completed.

- Chip seal in the Highgrove area has been completed.

- Crews will place type 1 & 2 slurry seal in Highgrove area over the chip seal.

- Crews will begin the placement of the Type II slurry seal on La Sierra and Blackburn.

- Striping and pavement markings will continue to be installed in the Temescal Canyon area and Riverside area.

- Raised pavement markers (RPM) are being installing throughout the project.

- Crews will continue with the application of Type I & II in the Highgrove and Riverside area.

- Crews will continue with post sweeping throughout the project.

- Please use caution, observe construction warning signs, and follow traffic control staff’s directions while travelling through the work zone. Thank you for your patience and understanding.



Steven Grayslurryseal
Van Buren Blvd. Resurfacing - Project Status

We have completed the pavement reconstruction on Van Buren Blvd. from the City of Riverside limits (Pine Court) to Capella Street in the Woodcrest Community of Riverside.

This week, the contractor will continue with minor improvements and upgrade the traffic signal at Mockingbird Canyon Road.

Please observe all construction warning signs, use caution, and follow the directions of traffic control staff to ensure safety.

We appreciate your patience and understanding as we work to improve the area.

Thank you.

Steven GrayVan Buren
El Cerrito Area Resurfacing Group 1 - Weekly Status

Pavement reconstruction and concrete improvements have begun on various streets in the El Cerrito area of Riverside County. The contractor is currently working on concrete cross-gutters.

This project is scheduled for completion in January 2025. Affected streets include:

  • Dry Gulch Road

  • Whiskey Creek

  • Sarsaparilla Drive

  • Long Branch Way

Please observe all construction warning signs, use caution, and follow the directions of traffic control staff to ensure safety.

We appreciate your patience and understanding during this project.

Thank you.

Yvette Munoz
Cornell Street Resurfacing - Project Status

Cornell Street Resurfacing - Project Status

We have started the pavement reconstruction and concrete improvements on Cornell Street, from Florida Avenue to Crest Drive, in the Community of East Hemet area. The majority of the concrete work has been completed, and crews are now focused on removing the existing asphalt pavement and preparing the roadway for new asphalt.

This project is scheduled for completion in February 2025. Please note that part of Cornell Street currently has a dirt surface, and we recommend using alternate routes during this phase.

For your safety, please observe all construction warning signs, use caution, and follow the directions of traffic control staff.

We appreciate your patience and understanding as we work to improve the roadway.

Thank you.

Steven Gray
Slurry Seal FY24-25 District 1,2,3 - Weekly Status

Slurry Seal FY24-25 District 1,2,3 - Weekly Status



- Repair/upgrade curb ramp throughout the project to meet ADA standard is completed.

- Weed Abatement in Districts 1,2 and 3 is completed.

- Type I and II slurry seal in the Woodcrest area is completed.

- Type I and Type II MSE in the Temescal Valley area is completed.

- Pavement Markings and the Second coat of striping in the Murrieta Hot Springs has been completed.

- Asphalt repairs throughout the project have been completed.

- Chip seal in the Highgrove area has been completed.

- Crews will place type 1 & 2 slurry seal in Highgrove area over the chip seal.

- Crews will begin the placement of the Type II slurry seal on La Sierra and Blackburn.

- Striping and pavement markings will continue to be installed in the Temescal Canyon area.

- Crews will continue with the application of Type I & II in the Highgrove and Riverside area.

- Crews will start and complete the application of the MSE Type II in Lake Elsinore area.

- Crews will continue with post sweeping throughout the project.

- Please use caution, observe construction warning signs, and follow traffic control staff’s directions while travelling through the work zone. Thank you for your patience and understanding.



Steven Grayslurryseal
Indiana Avenue, Grant Street, Harlow Avenue Resurfacing - Project Update

We have begun pavement reconstruction and concrete improvements on Indiana Avenue, Grant Street, and Harlow Avenue in the Home Gardens area. The contractor is currently working on concrete cross-gutters, curb & gutter, and some curb ramps on Harlow Avenue.

This project is scheduled for completion in February 2025. Please observe all construction warning signs, use caution, and follow the directions of traffic control staff to ensure safety during this time.

We appreciate your patience and understanding as we work to improve these roadways.

Thank you.

Steven Gray
NIGHTTIME LANE CLOSURES PLANNED on Ramona Expressway at Bridge St.

NIGHTTIME LANE CLOSURES PLANNED on Ramona Expressway at Bridge St.

Monday, Dec. 9, through Friday, Dec. 13, 2024 

9 p.m. to 5 a.m.

One lane on Ramona Expressway will be closed near Bridge Street. All traffic will be shifted to the other lane with flaggers assisting vehicles through the traffic control.

Please reduce speed and plan for delays.  

Gilman Springs Road is open to through traffic.  

CIERRES DE CARRILES NOCTURNOS PLANIFICADOS en Ramona Expressway en Bridge St. 

Del lunes 9 de diciembre al viernes 13 de diciembre de 2024 

9 p.m. a 5 a.m. 

Se cerrará un carril en Ramona Expressway cerca de Bridge Street. Todo el tráfico se cambiará al otro carril y los señalizadores ayudarán a los vehículos a pasar el control de tráfico.

Reduzca la velocidad y planifique los retrasos. 

Gilman Springs Road está abierta al tráfico.

Hotline: 877.277.5343

Website: www.rcproject.org/gilman

Linea directa: 877.277.5343

Sitio Web: www.rcproject.org/gilman

#GilmanSpringsRoad

Yvette Munozgilmanphase6
Slurry Seal FY24-25 District 4 & 5 - Weekly Status Update

Slurry Seal FY24-25 District 4,5 - Weekly Status Update


- Crack seal treatment continued w/two crews in Palm Desert to stay ahead of slurry team.

- Type 2 slurry seal work changed from Cabazon to Hemet.

- Crew worked on Saturday doing Type 2 slurry seal in Thousand Palms.

- CTI finished all striping punch list items at Lake Cahuilla. Just need water valve cover cleaned and load of excavated garbage removed to close out D5-0017.

- Two Crack seal crews scheduled for Saturday and Sunday in Redlands.

- Two crack seal crews and one slurry crew scheduled to continue Monday in Hemet.

- Please use caution, observe construction warning signs, and follow traffic control staff’s directions while travelling through the work zone. Thank you for your patience and understanding.


Steven Grayslurryseal
State Route 60 Truck Lanes project by RCTC, Construction Update, Week of December 2, 2024

State Route 60 Truck Lanes project by RCTC, Construction Update, Week of December 2, 2024

Nighttime alternating lane closures of eastbound 60 between Moreno Valley and Beaumont are scheduled the week of December 2.  www.rctc.org

The closures are needed to safely allow construction crews to perform roadway work. No detour will be required since one lane will remain open. Please allow for extra travel time. Closure details below:

Yvette Munozgilmanphase6
Slurry Seal FY24-25 District 4 & 5 - Weekly Status

Slurry Seal FY24-25 District 4 & 5 - Weekly Status

- Crack seal treatment continued with two crews in Thousand Palms to stay ahead of slurry team.

- Wide crack AC repairs completed in Redlands. Item 20 AC Surfacing now complete.

- Type 1 slurry seal work began in Thousand Palms.

- Type 2 slurry seal scheduled for Saturday in Thousand Palms.

- Type 2 slurry seal scheduled for Saturday in Cabazon.

- Two crack seal crews and one slurry crew scheduled to continue Monday in Thousand Palms.

- Please use caution, observe construction warning signs, and follow traffic control staff’s directions while travelling through the work zone. Thank you for your patience and understanding.

Steven Grayslurryseal