Construction Completed:
November 2017
Demolished existing bridge and northbound Indio Boulevard overcrossing, replaced with new six-lane bridge with bicycle lanes on each side and sidewalk on northbound side of Jefferson Street
Modified on and off-ramps:
Westbound I-10
Realigned, one-lane off-ramp
Indio Boulevard overcrossing on-ramp removed
Realigned, two-lane on-ramp from southbound Jefferson Street
New, two-lane loop on-ramp from northbound Jefferson Street
Eastbound I-10
Realigned, two lane off-ramp
Existing on-ramp from Jefferson Street overcrossing removed
New, two-lane loop on-ramp for northbound and southbound Jefferson Street
Add traffic signals at EB and WB on and off-ramps