Thank you for your patience while the Riverside County Transportation Department completes this important drainage improvement project. Temescal Canyon Road will open to traffic on Saturday, weather pending.

Project Update:
Utility work, concrete box culvert installation, and rock slope protection is complete. Final details with the new guard rail and paving are scheduled for Saturday completion, weather pending. Paving will be completed with temporary pavement markings for lane delineation.

Temescal Canyon Road will open while crews are on-site the week of July 29 to close out the project.