Temescal Canyon Road Widening Update, September 25, 2019
The contractor continues to work on storm drains, utility relocations, curb & gutter, and street paving along Temescal Canyon Road from Dawson Canyon Road to Dos Lagos Drive.
Current Construction and Traffic Restrictions:
Various utility and storm drain locations along the street are being worked on. Traffic flagging operations will direct traffic as needed to allow crews to work on the street at various locations.
Dirt is being placed behind the retaining wall south of Dos Lagos Drive.
Sidewalk, curb and gutter are being installed at various locations throughout the project area.
On Saturday, September 28, paving along the west side of Temescal Canyon Road north of Dawson Canyon Road
will be placed. Street lanes will not be closed for this work. On September 30, traffic will be switched to the newly paved west side of Temescal Canyon Road north of Dawson Canyon Road.