Clinton Keith Road Construction Notice for week of May 31-June 3

The contractor is scheduled to install all Thermoplastic Pavement Markings on Leon Road from Jean Nicholas Road to Max Gilliss Blvd. and on Max Gilliss Blvd. There will be lane closures, please use caution while travelling through this area. For Clinton Keith Road: The contractor is continuing the construction of a new proposed bridge crossing French Valley Creek.duled to install all Thermoplastic Pavement Markings on Leon Road from Jean Nicholas Road to Max Gilliss Blvd. and on Max Gilliss Blvd. There will be lane closures, please use caution while travelling through this area. For Clinton Keith Road: The contractor is continuing the construction of a new proposed bridge crossing French Valley Creek.

Continue Briggs Rd realignment.
Continue retaining wall construction.
Construct abutment footings.
Pile driving for bridge foundation: Ongoing