Clinton Keith Road - Weekly Status Sept. 11th - 15th

The proposed Clinton Keith Road from Leon Road to Winchester Road is progressing as planned. The contractor paved new asphalt (bottom layers) from Leon Road to SR-79. The construction drainage systems and concrete (curb, median, driveway, and sidewalk) are also progressing. Subcontractor resumed with the construction of various Traffic Signal systems. Murrieta Marketplace’s contractor is continuing with the installation of sewer and water lines along the new proposed Clinton Keith Road and on Benton Road. Please observe construction warning signs and use caution while using Benton Road.

Note: Briggs Road from Leon Road to Los Alamos Road is permanently CLOSED (NO ACCESS).