Connecting Our Communities

News

Project News

Clinton Keith Road - Weekly Status

The proposed Clinton Keith Road from Leon Road to Winchester Road is progressing as planned. The contractor is continuing with Rock Slope protection, shoulder, drainage systems, concrete (curb, median, driveways, and sidewalk), and traffic signal systems. Murrieta Marketplace’s contractor is continuing with the installation of sewer and water lines along the new proposed Clinton Keith Road and on Benton Road. Please observe construction warning signs and use caution while using Benton Road. Thank you for your patience and understanding!

Note: Briggs Road from Leon Road to Los Alamos Road is permanently CLOSED (NO ACCESS).