Gilman Springs Road Shoulder Widening and Median Project
PROJECT UPDATE: Gilman Springs Road will open to through traffic on Thursday, Nov. 21, by 11:30 p.m.weather permitting
SWIPE THROUGH -->
The week of Nov. 18, crews will complete:
- Concrete median construction
- Median rumble strips
- Roadway drainage
- Roadway resurfacing and striping
- Drainage culvert and wildlife crossing at Bridge Street.
Please reduce speed and drive with caution through the construction area.
UPCOMING WORK
Crews will not be working in the roadway during Thanksgiving week.
Please check social media pages @RivCoTrans and rcprojects.org/gilman for information about upcoming work schedules and traffic impacts.
Actualización del proyecto: Gilman Springs Road abrirá el 21 de noviembre a las 11:30 p.m. si el clima lo permite
DESLIZE -->
La semana del 18 de noviembre, los equipos completarán:
- Construcción mediana de hormigón.
- Franjas sonoras medianas
- Drenaje de carreteras
- Repavimentación y trazado de vías.
- Alcantarilla de drenaje y cruce de vida silvestre en Bridge Street.
Reduzca la velocidad y conduzca con precaución por el área de construcción.
PRÓXIMOS TRABAJOS
Los equipos no trabajarán en la carretera durante la semana de Acción de Gracias.
Consulte las páginas de redes sociales @RivCoTrans y rcprojects.org/gilman para obtener información sobre los próximos horarios de trabajo y los impactos del tráfico.
Hotline: 877.277.5343
Visit el sitio web del proyecto en www.rcprojects.org/gilman para obtener más información.
Linea Directa: 877.277.5343
#GilmanSpringsRoad