Nuevo Area Resurfacing Group - Weekly Status

Crews are continuing road improvements in the Nuevo Community. Starting Monday, February 3rd, and will begin pulverizing the existing asphalt concrete pavement on the following limits:

- 12th St from Reservoir Ave to North Dr

- Apricot Ave from Lakeview Ave to North Dr

- 13th St from Reservoir Ave to North Dr

- Stalder Ave from Ramona Ave to Lakeview Ave

- North Dr from Nuevo Rd to Lakeview Ave

Full-road closures on Lakeview Ave are no longer expected. Access to residential properties will be maintained at all times. Please drive with caution when driving on the pulverized asphalt concrete pavement, observe construction warning signs, and follow traffic control staff’s directions. Thank you for your patience and understanding.