Connecting Our Communities

News

Project News

Gilman Springs Road Completed

The County of Riverside Transportation Department completed the Gilman Springs Road Shoulder Widening and Median Project the week of March 24, 2025.

The project started in September 2024 and included the following work on approximately four miles of Gilman Springs Road:

• Constructed a new raised concrete median with reflective delineation and centerline rumble strips between Alessandro Blvd and approximately 1 mile south of Bridge Street

• Created 6-foot-wide paved shoulders so motorists can safely pull off the road

• Constructed an underground wildlife crossing at Bridge Street with wildlife fencing on Gilman Springs Road to deter animals from crossing on the roadway

• Constructed an approximately 1-mile-long northbound passing lane

• Completed drainage improvements and grading on shoulders and slope edges

Thank you for your patience during this project!



Steven Graygilmanphase6