Jurupa Grade Separation Project Update

Crews will be placing concrete for the retaining wall footings in the early morning hours of Fri., Sept., 2 beginning at 12 a.m. through 10 a.m. at Jurupa Road and Jurupa Detour Road. Please watch for trucks entering and exiting the jobsite, and noise associated with construction activity. 

#JurupaGradeSeparationProject

 

EXTENDED WORK HOURS:  

September 2 

Friday

12 a.m. - 10 a.m.

Jurupa Road and Jurupa Detour Road. 

Please watch for trucks entering and exiting the jobsite, and noise associated with construction activity. 

 

Thank you for you patience #JurupaValley. Crews continue working towards #ConnectingJurupaValley.

 

SUBSCRIBE: WEEKLY UPDATES

http://www.JurupaGradeSeparation.com

Steven Gray
Hamner Ave. Bridge & Widening Project Update

#HamnerAveProject

TRAFFIC CONTROL:

Monday and Wednesday

Aug. 29 and 31

9 a.m. - 3 p.m.

Hamner Ave. at Citrus St.

Alternating lane closures, watch for traffic flagging.

Thank you #NorcoCA and #Eastvale for REDUCING your SPEED in the project area. 

Steven Gray
San Jacinto Avenue Resurfacing - Weekly Update

We completed about 90% of San Jacinto Avenue improvements from Thornton Avenue to Florida Avenue in the East Hemet area. The contractor is working on Traffic Stripe, Pavement Markings, roadside signs, and minor repairs. Please continue use caution while travelling through. Thank you for your patience and understanding.

Steven Gray
Mayberry Avenue Sidewalk - Weekly Update

The contractor is scheduled to complete Mayberry Avenue sidewalk project this week. Thank you all for your outstanding supports and understanding.

Steven Gray
Mountain View Road Resurfacing - Weekly Video Update

The contractor is currently working on the replacement of concrete sidewalk, curb ramps, cross-gutter, and other improvements on Mountain View Road in the City of Desert Hot Springs. We are scheduled to install new concrete Dip Crossing and will have to close Mountain View Road on 24 AUGUST 2022 for 10 to 14 days. We provided Construction Notice and will place signage for detour route as soon as possible.

Steven Gray
San Jacinto Avenue Resurfacing - Weekly Update

We completed the replacement of asphalt pavement on San Jacinto Avenue from Florida Avenue to Thornton Avenue in the east Hemet area. The contractor is scheduling to paint traffic stripe, pavement markings, and other minor improvements this week. Please continue use caution while travelling through the work zone. Thank you for your patience and understanding.

Steven Gray
Clinton Keith Rd Week of August 15-19 Construction Notice Video

Leon Road and Max Gilliss Blvd. Resurfacing is nearly completed pending some minor work. The contractor is continuing with the construction of the proposed bridge, culverts, traffic signal system, and various drainage systems for Clinton Keith Road from Leon Road to Winchester Road/Benton Road in the French Valley/Murrieta area.

The contractor is actively constructing new a proposed bridge over French Valley Creek, Culverts, earthwork, and traffic signals for Clinton Keith Road connecting from Leon Road to Winchester Road (SR 79)/Benton Road. Note: Briggs Road from Leon Road to Los Alamos is CLOSED.

El Toro Road and Dexter Avenue Sidewalk - Weekly Update

Majority of concrete work including sidewalk, curb & gutter, cross-gutter, and driveways has been completed. The contractor is working on the remaining sidewalk and storm drainage structures. Please continue use caution while travelling through the work zone. We are scheduling to remove the existing roadway starting on 19 August 2022 and are scheduled to pave the new roadway during the weekend (material and weather pending.) We will do our best to accommodate school traffic for Temescal Canyon High School including work on weekends. Thank you for your patience and understanding.

Steven Gray
Thousand Palms Canyon Road Resurfacing - Weekly Update

Thank you everyone for a successful project! With outstanding supports from survey, material lab, and other county staff the contractor was able to complete this project about a month early. Thanks to the public for cooperation and understanding during construction.

Steven Gray
El Toro Road and Dexter Avenue Sidewalk - Weekly Update

We completed about 80% of concrete sidewalk, Curb & Gutter, Cross-Gutter and Driveways along El Toro Road and Dexter Avenue in the North Lake Elsinore area. The contractor is continuing construction new proposed sidewalk and replacing Storm Drain Inlets on Dexter Avenue. Please continue use caution and observe construction warning signs at various locations.

Steven Gray
San Jacinto Avenue Resurfacing - Weekly Update

We are removing existing asphalt pavement and install new asphalt on San Jacinto Avenue from Florida Avenue to Thornton Avenue in the East Hemet area. Please use caution or use alternate route due to large equipment and trucks constantly moving in the work zone. Thank you for your patience and understanding. This major work is scheduled to complete this week.

Steven Gray
San Jacinto Avenue Resurfacing - Weekly Update

We completed all concrete work including Cross-Gutter, Driveways, Curb & Gutter, Curb Ramps, and Dip Crossing. The contractor is working on removing and replacing asphalt pavement on San Jacinto Avenue starting from Thornton Avenue towards Florida Avenue. Please continue use caution due to large construction equipment and many trucks moving around within the work zone.

Steven Gray
Thousand Palms Canyon Road Resurfacing - Weekly Update

The contractor is working on the shoulder, pavement traffic striping, and rumble strips on Thousand Palms Canyon Road from Dillon Road to Washington Street/Ramon Road in the Desert Hot Springs area. Please continue to use caution while travelling through the work zone. Thank you for your patience and understanding.

Steven Graythousandpalms
Jurupa Grade Separation Project CONSTRUCTION UPDATE 8/8/22

Traffic control on Felspar Street is expected Monday through Friday, Aug. 8-12, from 6 a.m. to 4 p.m. Crews Will be potholing for utilities in the area. 

#JurupaGradeSeparationProject

 

SUBSCRIBE: WEEKLY UPDATES

http://www.JurupaGradeSeparation.com

 

TRAFFIC CONTROL:  

August 8-12

Monday - Friday

6 a.m - 4 p.m.

NB and SB Felspar St. from north of Jurupa Rd. to Galena St.

Expect traffic flagging.

 

BUSINESS ACCESS REMAINS OPEN 

>Use Van Buren Blvd. to Rutile St.to Galena St. to Felspar St. 

>or Van Buren Blvd. to Pedley Rd. to Jurupa Rd.-->

#CleanersPlus

#DoninosJV

#DonutTyme

#DrTooth

#ElCorralBajaGrill

#FamilyDiscount

#FMIRealtyServices

#HiDefInc

#JackintheBoxJV

#JDsMissionSteakhouse

#LuckyWokJV

#MariesBeautySalon

#MetrobyTMobileJV

#MomiasNursery

#PanaderiaJaliscoBakery

#PizzaKing

#PlazaLiquor

#SouthridgeCycling

#StateFarmTroyManning

#StaterBrosJV

#SubwayJV

#TitosSmogCheckStarStation

#YourHairCenter

>Use Jurupa Detour Rd. or Rutile St.-->

#ArmandosRadiatorandMuffler

#JurupaDairyandGasPropaneRefill

#PerezMarket

 

JGS BUSINESS DIRECTORY: https://www.jurupagradeseparation.com/business-directory/

#ShopJurupaValley BUY local

Steven Gray