The proposed Clinton Keith Road from Leon Road to Winchester Road/Benton Road is progressing on schedule. The contractor is continuing construction on a new bridge over French Valley Creek, earthwork, and other improvements. Note: Briggs Road from Leon Road to Los Alamos Road is still CLOSED.
We completed the drainage system and all concrete facilities. From September 6, the contractor is scheduled to remove existing asphalt pavement on Soboba Street from Stetson Avenue towards Florida Avenue in the East Hemet area. The roadway surface will be uneven dirt, please use caution and observe construction warning signs while traveling through the work zone. Please use an alternate route if possible. Thank you for your understanding!
We completed the construction of the concrete Dip Section crossing Mountain View Road, and paved the new bottom layer of asphalt from Dillon Road towards City of Desert Hot Springs. The contractor is continuing with the reconstruction of asphalt pavement in the City of Desert Hot Springs and scheduled to pave the top layer of asphalt soon. Note: Mountain View Road is open to traffic. Please continue use caution while travelling through due to uneven dirt surfaces. Thank you for your patience and understanding.
The proposed Clinton Keith Road from Leon Road to Winchester Road/Benton Road is progressing on schedule. The contractor is continuing on construction of a new bridge over French Valley Creek, earthwork, and other improvements. The contractor is scheduled to install, and to replace, some roadside signs on Leon Road and Max Gilliss Boulevard. Note: Briggs Road from Leon Road to Los Alamos Road is still CLOSED.
We are working with Southern California Edison (SCE) to relocate or upgrade SCE’s facilities within our new proposed sidewalk. There will be electrical outages (SCE will notified affected residents). The contractor is scheduled to grind existing pavement and pave new asphalt on El Toro Road and Dexter Avenue in the North Lake Elsinore area from September 7th to September 10th (Saturday). Please use caution and observe construction warning signs while travelling through the work zone. Thank you for your patience and understanding.
We started the Soboba Street Resurfacing project and are working on concrete curb & gutter, cross-gutter, and drainage from Mayberry Avenue to Florida Avenue in the East Hemet area. The contractor is scheduled to remove existing asphalt surface and pave new asphalt starting September 6, 2022 from Stetson Avenue to Florida Avenue. Please use caution and observe traffic warning signs while travelling through.
The contractor and Edison are doing minor work and cleaning the project site this week. We are scheduled to remove existing asphalt on Dexter Avenue on September 7, 2022 and pave new asphalt on September 10, 2022. Thank you for your understanding.
Mountain View Road shall be opened by 9/3/2022. We are working with the contractor to properly open the road at end of 9/2/2022.
We completed majority of concrete work in the City of Desert Hot Springs area. The contractor is aggressively with the reconstruction of Mountain View Road from Dillon Road to Hacienda Avenue. Mountain View Road is CLOSED to through traffic until September 3, 2022. Thank you for your patience and understanding.
We are working aggressively on the construction of the new proposed bridge and solving utility conflicts. The construction progress is moving well. Reminder: Briggs Road from Leon Road to Los Alamos Road is CLOSED.
Crews will be placing concrete for the retaining wall footings in the early morning hours of Fri., Sept., 2 beginning at 12 a.m. through 10 a.m. at Jurupa Road and Jurupa Detour Road. Please watch for trucks entering and exiting the jobsite, and noise associated with construction activity.
#JurupaGradeSeparationProject
EXTENDED WORK HOURS:
September 2
Friday
12 a.m. - 10 a.m.
Jurupa Road and Jurupa Detour Road.
Please watch for trucks entering and exiting the jobsite, and noise associated with construction activity.
Thank you for you patience #JurupaValley. Crews continue working towards #ConnectingJurupaValley.
SUBSCRIBE: WEEKLY UPDATES
#HamnerAveProject
TRAFFIC CONTROL:
Monday and Wednesday
Aug. 29 and 31
9 a.m. - 3 p.m.
Hamner Ave. at Citrus St.
Alternating lane closures, watch for traffic flagging.
Thank you #NorcoCA and #Eastvale for REDUCING your SPEED in the project area.
We completed about 90% of San Jacinto Avenue improvements from Thornton Avenue to Florida Avenue in the East Hemet area. The contractor is working on Traffic Stripe, Pavement Markings, roadside signs, and minor repairs. Please continue use caution while travelling through. Thank you for your patience and understanding.
The contractor is scheduled to complete Mayberry Avenue sidewalk project this week. Thank you all for your outstanding supports and understanding.
The contractor is currently working on the replacement of concrete sidewalk, curb ramps, cross-gutter, and other improvements on Mountain View Road in the City of Desert Hot Springs. We are scheduled to install new concrete Dip Crossing and will have to close Mountain View Road on 24 AUGUST 2022 for 10 to 14 days. We provided Construction Notice and will place signage for detour route as soon as possible.