Connecting Our Communities

Ontario Avenue Widening and Restriping Project

Ontario Avenue Widening and Restriping Project

Project Overview

The County of Riverside Transportation Department (County) proposes to widen and restripe Ontario Avenue from State Street to Diplomat Avenue to provide a four-travel lane facility consisting of two southbound lanes, two northbound lanes, one two-way left-turn lane, and two marked on-street bike lanes. The roadway is currently striped for a three-lane configuration with two southbound lanes, one northbound lane, one two-way left-turn lane, and no bike lanes. The project would entail resurfacing the existing roadway and widening along the east side between Diplomat Avenue and Rising Sun Road for a consistent 64-feet-wide curb-to-curb width. Other project improvements include the conversion of existing drainage inlets to catch basins and completing a missing sidewalk segment along the west side of Ontario Avenue between State Street and Piute Creek Road.

Additional Project Details

Limits: State Street to Diplomat Avenue

Length: Approximately 0.58  miles (3,062 feet)

District: 2

Community: El Cerrito

Project Schedule

  • Environmental Phase Clearance: Spring 2025

  • Final Design: Winter 2025

  • Right of Way: Fall 2025 (Tentative)

  • Construction Start: Spring 2026 (Tentative)

  • Construction End: Fall 2026 (Tentative)

Project Documents


☎ PROJECT CONTACT

Alfredo Martinez
(951) 955-0086