Nuevo Area Rehabilitation

Limits: Varies, see below
Length: Approximately 7,800 feet
District: 5
Community: Nuevo 

The County of Riverside Transportation Department proposes to rehabilitate the following roads in the Nuevo Area. The roads are all classified as being Local Roads in the County of Riverside General Plan. The roads range from 28-44 feet wide with curb/gutter and sidewalk. The proposed improvements consist of removing the existing roadway, cement treating the base, and overlaying Hot Mix Asphalt (HMA).

  1. Porter Street from Menifee Road to Approximately 1,000 feet West of Penasco Circle

  2. Mirileste Drive from Menifee Road to Approximately 200 feet West of Pasito Street

  3. Via Santana from 150 ft Notth of Mirileste Drive to Approximately 200 feet South of Pablo Street

  4. Penasco Circle from Porter Street to Approximately 800 feet South of Mecheka Drive

  5. Macheka Drive from Mirileste Drive to Penasco Circle

  6. Pasito Street from Mirileste Drive to Approximately 500 feet East of Mirileste Drive

  7. Pablo Street from Via Santana to Approximately 200 feet east of Via Santana

Additional improvements include:

  • Reconstruction of concrete sidewalk, curb/gutter, driveway approach, cross gutter, and spandrel

  • Placement of safety edge and shoulder backing

  • Utility adjustments

  • Striping of roadway, including pavement markers and reflectors

No additional right-of-way or temporary construction easements will be required to construct the proposed improvement. The project improvements will not raise the existing roadway profiles.

 

PROJECT SCHEDULE

Environmental Clearance: December 2017
Final Design: November 2017
Construction Start: April 2018
Construction Completion: June 2018