Connecting Our Communities

News

Project News

Dexter Ave & El Toro Rd Sidewalk Weekly Update- Week ending July 29, 2022

90% of concrete Curb & Gutter, Driveways, and Sidewalk have been completed. The contractor continues to prepare the ground for the remaining of the proposed sidewalk along Dexter Avenue. Please use caution and observe “OPEN TRENCH” signs along the shoulder. Thank you for your patience and understanding.

Yvette Munozdexter