Connecting Our Communities

News

Project News

Posts tagged dexter
Dexter Ave & El Toro Rd Sidewalk Weekly Update- Week ending July 29, 2022

90% of concrete Curb & Gutter, Driveways, and Sidewalk have been completed. The contractor continues to prepare the ground for the remaining of the proposed sidewalk along Dexter Avenue. Please use caution and observe “OPEN TRENCH” signs along the shoulder. Thank you for your patience and understanding.

Yvette Munozdexter
Dexter Ave & El Toro Rd Sidewalk - Weekly Update

Construction update for the week ending 7/21/22. RivcoTrans continues with the construction of a new proposed sidewalk along El Toro Road and Dexter Avenue in the North Lake Elsinore area. Please use caution and observe flaggers’ instructions while travelling through the work zone. Thank you for your patience and understanding.

Yvette Munozdexter
El Toro Road and Dexter Avenue Sidewalk - Weekly Newsletter

We are currently working on the construction of Curb & Gutter along El Toro Road and east side of Dexter Avenue in the North Lake Elsinore area. Please observe “OPEN TRENCH” and use caution while travelling through this area. Thank you for your patience and understanding.

Steven Graydexter
Dexter Ave. & El Toro Rd. Sidewalk Weekly Update - 07/05/22

This week the County is removing existing asphalt pavement and ground for the new proposed sidewalk along El Toro Road in front of Temescal Canyon High School.. Please use caution while traveling through the work zone.

 

Yvette Munozdexter