Ramona Expressway Median project update, March 21, 2023

The contractor has installed nearly 40% of the median and will continue to work easterly from Nuevo to Bridge Street. We will continue the construction from Lakeview Avenue to Bridge Street with a lane Closure Nightly from 8:00 PM until 5:00 AM (weather permitting). Please use caution due to the newly raised median and obey traffic control personnel while traveling through the area.  #ramonamedian

***No work scheduled Monday, 3/20 to Wednesday 3/22 due to rain. Will resume Thursday 3/23 night and continue on Friday and Sunday nights.