Slurry Seal FY 22-23 Dist. 1 &2 - Weekly Status

Lake Elsinore area: Completed.

Coronita area: Continue to install Traffic Stripe and Pavement Markings to applicable streets.

Home Gardens area: Continue to install Traffic Stripe and Pavement Markings to applicable streets

Woodcrest area: Continue to install Traffic Stripe and Pavement Markings to applicable streets.

Cajalco Road: Completed.

The project is anticipated to complete on June 28, 2023. Contractor is working on correcting minor discrepancies.

Please visit our Transportation website for more information regarding Slurry Seal applications.