- Repair/upgrade curb ramp throughout the project to meet ADA standard is completed.
- Weed Abatement in Districts 1,2 and 3 is completed.
- Type I and II slurry seal in the Woodcrest area is completed.
- Type I and Type II MSE in the Temescal Valley area is completed.
- Pavement Markings and the Second coat of striping in the Murrieta Hot Springs has been completed.
- Asphalt repairs throughout the project have been completed.
- Chip seal in the Highgrove area has been completed.
- Crews will place type 1 & 2 slurry seal in Highgrove area over the chip seal.
- Crews will begin the placement of the Type II slurry seal on La Sierra and Blackburn.
- Striping and pavement markings will continue to be installed in the Temescal Canyon area and Riverside area.
- Raised pavement markers (RPM) are being installing throughout the project.
- Crews will continue with the application of Type I & II in the Highgrove and Riverside area.
- Crews will continue with post sweeping throughout the project.
- Please use caution, observe construction warning signs, and follow traffic control staff’s directions while travelling through the work zone. Thank you for your patience and understanding.