The contractor completed the slurry seal operation in the Temecula, French Valley, and Homeland areas. The contractor is scheduled to apply slurry seal to various streets in Hemet/Vale Vista area on Tuesday, 7/18/23.


Streets Included 7/18/23

- Meadow Grove St

- Avocet Cir

- Hazelwood

- Lincoln Ave

- Grovewood Cir

- Springwood Cir

- Peartree Lane

- Fore Dr

- Sunshine Ct

- Frazier/ Alto/ Ardmore/ Deanne

Note: Pavement delineations are scheduled at night (9:00PM – 5:00AM) on various days. Traffic impact is minimal.

Please follows construction warning signs and DO NOT park vehicles or drive on street with posted “NO PARKING” signs with the applicable date. Thank you for your cooperation and understanding.

Please visit our Transportation website for more information regarding Slurry Seal applications.