Project Update- District 3, Slurry Seal & Curb Ramp Accessibility Project

The contractor completed the slurry seal operation in the Temecula, French Valley, and Homeland areas. The contractor is scheduled to apply slurry seal to various streets in Hemet/Vale Vista area including Gilman Springs Road east of Sanderson Avenue/SR 79. (Schedule will follow soon).

Pavement Delineations will be installed for Homeland area and completed slurry seal areas in Hemet area.

Pavement delineations are scheduled at night (9:00PM – 5:00AM) on various days. Traffic impact is minimal.

Please follows construction warning signs and DO NOT park vehicles or drive on street with posted “NO PARKING” signs with applicable date. Thank you for your cooperations and understanding.

Please visit our Transportation website for more information regarding Slurry Seal applications. www.rcprojects.org/slurryseal