- We finished slurry seal in Morgan Hills and Murrieta Hot Springs area.

- Pavement Markings and the First coat of striping has been completed in the Morgan Hill area.

- Asphalt repairs have been completed throughout the project.

- ADA ramps have been completed throughout the project.

- Contractor will continue with the crack seal in the Temescal Canyon area and touch up work.

- The prime contractor will continue with post sweeping throughout the project.

- Striping and Pavement Markings will be installed in Murrieta Hot Springs, Perris, and Hemet areas.

- Please use caution, observe construction warning signs, and follow traffic control staff’s directions while travelling through the work zone. Thank you for your patience and understanding.