Slurry Seal FY24-25 District 1, 2, 3 - Weekly Status
Slurry Seal FY24-25 District 1, 2, 3 - Weekly Status
- We finished slurry seal in Morgan Hills and Murrieta Hot Springs area.
- Pavement Markings and the First coat of striping has been completed in the Morgan Hill area.
- Asphalt repairs have been completed throughout the project.
- ADA ramps have been completed throughout the project.
- Contractor will continue with the Crack Treatment with Crack Seal in the Riverside area.
- Contractor will continue with the slurry seal in the Perris area with the first crew.
- The prime contractor will have the second crew perform repair work in Hemet.
- Striping lay out should start this week on Willows, Washington and both Pourroy sections.
- Micro-Milling will start on Wednesday in Hemet and then Thursday and Friday in Temescal Valley.
- Please use caution, observe construction warning signs, and follow traffic control staff’s directions while travelling through the work zone.
Thank you for your patience and understanding.