- Crack seal treatment continued with two crews in Thousand Palms to stay ahead of slurry team.
- Wide crack AC repairs completed in Redlands. Item 20 AC Surfacing now complete.
- Type 1 slurry seal work began in Thousand Palms.
- Type 2 slurry seal scheduled for Saturday in Thousand Palms.
- Type 2 slurry seal scheduled for Saturday in Cabazon.
- Two crack seal crews and one slurry crew scheduled to continue Monday in Thousand Palms.