- Crack seal treatment continued w/two crews in Palm Desert to stay ahead of slurry team.

- Type 2 slurry seal work changed from Cabazon to Hemet.

- Crew worked on Saturday doing Type 2 slurry seal in Thousand Palms.

- CTI finished all striping punch list items at Lake Cahuilla. Just need water valve cover cleaned and load of excavated garbage removed to close out D5-0017.

- Two Crack seal crews scheduled for Saturday and Sunday in Redlands.

- Two crack seal crews and one slurry crew scheduled to continue Monday in Hemet.

- Please use caution, observe construction warning signs, and follow traffic control staff’s directions while travelling through the work zone. Thank you for your patience and understanding.