Jurupa Gradae Separation - Updated Construction Alert - Week of May 26

‼️ UPDATED ‼️ CONSTRUCTION ALERT - Week of May 26, 2025 
Long-term intersection closure begins and traffic control is planned throughout the project area this week. 

 

TRAFFIC IMPACTS: 
⚠️  Long-term intersection closure begins at Jurupa Road and Felspar Street 
Tues., May 27, for 18 months | Businesses are OPEN during construction 

-Access to the Stater Bros. Shopping Plaza is available from Jurupa Road and Felspar Street 
-Access to the shopping plaza west of Felspar Street is available from Felspar Street 
-Please use the posted detours 

The closure is necessary to perform excavation, construct the railroad bridge, and adjust the intersection grade to connect with the Jurupa Road underpass. 
 
⚠️  Lane closures planned on Van Buren Boulevard outside NB lane 
Tues. – Sun. | May 27 – June 1 | 6 a.m. to 6 p.m. 
-Outside northbound lane closures planned from 52nd Street to Jurupa Connector Road to accommodate railroad track work 

 

⚠️  Jurupa Connector Road and Van Buren Boulevard traffic signal on flash 
Tues. and Wed. | May 27 and 28 | 9 a.m. to 4 p.m. 
-Intersection signals will be on flash with traffic control in place to install traffic signal equipment 
-All vehicles must STOP at the intersection 🛑 

 

This information may change due to weather or field conditions. 

 

Construction Hotline: 800-679-9570 
More info: www.JurupaGradeSeparation.com 