The Mayor Berwin Hanna Bridge on Hamner Avenue is now OPEN!

Project Milestone 

The Mayor Berwin Hanna Bridge on Hamner Avenue is now OPEN

 

The newly constructed 1,200-foot-long, six-lane bridge over the Santa Ana River is now open in both directions. Crews will continue working on the bridge barrier railing, the multipurpose trail, irrigation, landscaping, and other punch list items through early Fall 2024. 

 

Watch for intermittent lane closures and traffic control in the project area.

 

Stay updated with our project website at www.hamneraveproject.com

 

Hotline: 877-278-7606

 

#HamnerAve #NorcoCa 

Steven GrayHamner
NIGHTTIME ROAD CLOSURE - Hamner Ave Bridge Project

Hamner Ave. Bridge Project Continued Nighttime Road Closures

Road Closures planned on Hamner Ave. from Detroit St. to Citrus St.
 Wednesday and Friday nights 
10 p.m. to 5 a.m.

TRAFFIC IMPACTS 
Nighttime Road Closures Planned 
Wednesday, Aug. 21 -Friday, Aug. 23

Please follow posted detour.

BRIDGE OPENS | TRAFFIC PATTERN CHANGE

The northbound bridge span will open Saturday, Aug. 24 and traffic will shift onto both bridge spans. Traffic lanes on Hamner Ave. north and south of the bridge will be open in both directions.

Please plan for delays and use alternate routes.

Hotline: 877.278.7606

 Visit our project website at www.hamneraveproject.com for more information.

 

#HamnerAve #norcocalifornia 

Yvette MunozHamner
Construction Alert: Nighttime Road Closure - Hamner Ave Bridge

NIGHTTIME ROAD CLOSURE

Monday through Tuesday | Aug. 19, 20
10 p.m. to 5 a.m. 

Full road closure on Hamner Ave. from Detroit St. to Citrus St., use the posted detour to River Rd.

Please plan for delays and use alternate routes.

Hotline: 877.278.7606

Visit our project website at hamneraveproject.com.

#HamnerAve #Norco 

Yvette MunozHamner
HAMNER AVE CONSTRUCTION ALERT - FULL ROAD CLOSURE 

FULL ROAD CLOSURE 

Thursday and Friday nights| Aug. 8, 9 | 10 p.m. to 5 a.m. 

Full road closure on Hamner Ave. from Detroit St. to Citrus St., use posted detour to River Rd. 

Please plan for delays and use alternate routes. 

Hotline: 877.278.7606 

Visit our project website at hamneraveproject.com for the latest updates. 

#HamnerAve #Norco 

@CiyofEastvale @RivcoTrans @CityofNorco 

Steven GrayHamner
Construction Alert: August 2, 2024 - Hamner Ave Bridge & Widening Project

HAMNER AVENUE NIGHTTIME LANE CLOSURE

Friday night, Aug. 2 10 p.m. to 5 a.m.

An additional nighttime lane closure is necessary from Detroit to Citrus streets to complete this week's bridge repair work. Only one lane will be open for traffic; vehicles will be flagged through the area, one direction at a time. Expect delays, please use alternate routes.

Yvette MunozHamner
Hamner Ave. Bridge - CONSTRUCTION ALERT - Nighttime Lane Closures

Hamner Ave. Bridge



CONSTRUCTION ALERT:

Nighttime Lane Closures

Wednesday, July 31, and August 1

10 p.m. to 5 a.m.

Nighttime lane closures are planned from Detroit to Citrus streets. One lane will be open on Hamner Avenue during nighttime work. Traffic flaggers will assist motorists through the construction zone.

Please reduce speed and watch for crews working in the area.

Expect delays, please use alternate routes.

Hotline: 877.278.7606

Visit our project website at hamneraveproject.com for the latest updates.

#HamnerAve #Norco

@CityofNorco @CityofEastvale @Rivctotrans @Silverlakespark @Norcoareachamber



Steven GrayHamner
HAMNER AVE. BRIDGE PROJECT - ALERT - Road Closure May 22nd-24th

HAMNER AVE. BRIDGE PROJECT - ALERT



Road Closure: Westbound Detroit Street at Hamner Ave. May 22-24



Week of May 20, 2024

Day Time Road Closure

TRAFFIC IMPACTS

Westbound Detroit Street will be closed at Hamner Avenue.

Eastbound Detroit Street remains open.

Wednesday, Thursday and Friday, May 22—24

9 a.m. to 3 p.m.

Please follow the detour for local access.

Please plan for extra travel time and reduce speed in the area.

The closure is necessary for crews to complete a waterline relocation in the intersection.

This information may change due to weather or field conditions.



#HamnerAveProject #NorcoCa

@CityofEastvale @NorcoAreaChamber @CityofNorco



Steven GrayHamner
Hamner Ave Project - Daytime Road Closure ALERT

#HamnerAveProject #Norcoca 

 

‼️ Daytime Road Closure ‼️

 

Hours: 9 a.m. to 3 p.m. 

 

Friday, March 15, & intermittently the week of March 18. 

 

Detroit St. will be closed to through traffic at Hamner Ave. during daytime work.

 

Please use alternate routes. 

Add extra time for travel and follow detour for local access.

 

SUBSCRIBE at 

http://www.hamneraveproject.com/updates/

 

STAY CONNECTED 

on IG

@hamneraveproject and on FB

@Hamner Avenue Bridge and Widening Project. 

 

SUBSCRIBE AT

http://

www.hamneraveproject.com/updates/

STAY CONNECTED

on IG @hamneraveproject 

and on FB @Hamner Avenue Bridge and Widening

Project.

 

PROJECT REMINDER:

 

🚌-->REDUCE SPEED to 35 mph in the project area, watch for crews working on the shoulder from Detroit to Citrus streets, along the length of the bridge, and in the center median from Alhambra to Detroit streets.

 

❌NO PEDESTRIAN ACCESS across the bridge❌

 

USE @RiversideTransitAgency ROUTE 3

Check out RTA's website for more information https://

www.riversidetransit.com/

 

Route 3:

 

https://www.riversidetransit.com/images/

DOWNLOADS/ MAPS_SCHEDULES_PDFS/ Route%203%20%7C%20Eastvale,%20Norco,%20Corona%20Transit%20Center.pdf

 

###

 

Tag: @cityofnorco

@cityofeastvale

@norcoareachamber

Steven GrayHamner
Hamner Ave Project - UPDATE

#HamnerAveProject

#NorcoCA

DAYTIME ROAD CLOSURE: TRAFFIC IMPACTS

Detroit Street will be closed to through traffic at Hamner Avenue during daytime work.

Tuesday - Thursday

Feb. 6 -8

9 a.m. to 3 p.m.

Use alternate routes, add extra time for travel, and follow detour for local access.

PROJECT REMINDER:

REDUCE SPEED to 35 mph in the project area, watch for crews working on the shoulder from Detroit to Citrus streets, along the length of the bridge, and in the center median from Alhambra to Detroit streets.

NO PEDESTRIAN ACCESS across the bridge

USE @RiversideTransitAgency ROUTE 3

Check out RTA’s website for more information https://www.riversidetransit.com/

Route 3:

https://www.riversidetransit.com/.../Route%203%20%7C...

SUBSCRIBE at http://www.hamneraveproject.com/updates/

STAY CONNECTED on IG @hamneraveproject and on FB @Hamner Avenue Bridge and Widening Project.

Steven GrayHamner
Hamner Ave. Week of Nov. 20 - Construction Update

#HamnerAveProject

 

PROJECT PROGRESS

Crews continue to work on eastern span bridge interior construction with a concrete placement scheduled for Dec. 1. Construction throughout the project area continues.

 

REDUCE SPEED to 35 mph in the project area, watch for crews working on the shoulder from Detroit Street to Citrus Street and along the length of the bridge. 

 

PEDESTRIAN ACCESS available on the western side of Hamner Avenue from Schleisman Road to the southern crosswalk at Citrus Street. 

 

NO PEDESTRIAN ACCESS ACROSS THE BRIDGE in this phase of the project. 

 

PLEASE USE RTA @riversidetransit Route003

Bus stops at 

Taft Street and Hamner Avenue (northbound)

AND

Citrus Street west of Hamner Avenue (southbound)

Please visit riversidetransit.com for route specific information.

 

SUBSCRIBE at http://www.hamneraveproject.com/updates/ 

 

STAY CONNECTED on IG @hamneraveproject and on FB @Hamner Avenue Bridge and Widening Project

Steven GrayHamner
Hamner Ave. Project - Week of November 13

#HamnerAveProject

 

Week of November 13

 

PROJECT PROGRESS

Construction continues on the bridge interior with a milestone concrete placement planned for late November, weather permitting. Crews completed curb and gutter concrete placement and will finish sidewalks from the bridge to Citrus Street.

 

REDUCE SPEED to 35 mph in the project area and watch for crews working on the shoulder at Detroit Street, Citrus Street and across the bridge. 

 

PEDESTRIAN ACCESS is available on the western side of Hamner Avenue from Schleisman Road to the southern crosswalk at Citrus Street. 

 

NO PEDESTRIAN ACCESS ACROSS THE BRIDGE in this phase of the project. 

 

PLEASE USE RTA @riversidetransit Route003, with stops at Taft Street and Hamner Avenue (northbound), and on Citrus Street west of Hamner Avenue (southbound). Please visit riversidetransit.com for information.

 

SUBSCRIBE at http://www.hamneraveproject.com/updates/ 

 

STAY CONNECTED on IG @hamneraveproject and on FB @Hamner Avenue Bridge and Widening Project. 

Video Block
Double-click here to add a video by URL or embed code. Learn more
Steven GrayHamner
Hamner Ave Project - Week of October 23 ALERT

#HamnerAveProject

 

Week of October 23

 

TRAFFIC FLAGGING 

Thursday, Oct. 26

9 a.m. - 2 p.m.

Watch for crews on Hamner Avenue from Detroit to Citrus streets restriping pavement in the area. 

Add extra time for travel. 

 

REDUCE SPEED to 35 mph in the project area and watch for crews working on the shoulder at Detroit Street, Citrus Street and across the bridge. 

 

PEDESTRIAN ACCESS is available on the western side of Hamner Avenue from Schleisman Road to the southern crosswalk at Citrus Street. 

 

NO PEDESTRIAN ACCESS ACROSS THE BRIDGE in this phase of the project. 

 

PLEASE USE RTA @riversidetransit Route003, with stops at Taft Street and Hamner Avenue (northbound), and on Citrus Street west of Hamner Avenue (southbound). Please visit riversidetransit.com for information.

 

SUBSCRIBE at http://www.hamneraveproject.com/updates/ 

STAY CONNECTED on IG @hamneraveproject and on FB @Hamner Avenue Bridge and Widening Project. 

Steven GrayHamner
Hamner Ave. Project Construction Update Week of September 11th

#HamnerAveProject

 

Check out the latest time lapse video of crews placing concrete on the eastern span of the new Mayor Berwin Hanna Bridge.  

REMINDERS:

REDUCE SPEED to 35 mph and watch for crews working on the shoulder north of Citrus Street and behind k-rail at Detroit Street. Please WATCH for trucks entering and exiting the jobsite at multiple locations. 

 

PEDESTRIAN ACCESS is available on the western side of Hamner Avenue from Schleisman Road to the southern crosswalk at Citrus Street. 

 

NO PEDESTRIAN ACCESS ACROSS THE BRIDGE is available in this phase of the project. 

PLEASE USE RTA @riversidetransit Route003, with stops at Taft Street and Hamner Avenue (northbound), and on Citrus Street west of Hamner Avenue (southbound). Please visit riversidetransit.com for information.

 

SUBSCRIBE at http://www.hamneraveproject.com/updates/ 

STAY CONNECTED on IG @hamneraveproject and on FB @Hamner Avenue Bridge and Widening Project.

Steven GrayHamner
HAMNER AVENUE PROJECT Week of July 10

#HamnerAveProject

 

LANE CLOSURE Tuesday, July 11 | 7 a.m. to 3 p.m.

Northbound Hamner Avenue at Citrus Street right turn lane into SilverLakes will be closed.

Right turn available from the middle lane. 

Watch for crews working in the roadway and on the shoulder.

 

EXTENDED WORK HOURS Monday - Saturday | 5 a.m. - 10 p.m. 

Crews continue bridge foundation work including pile driving activities.

Expect construction pounding noises from 7 a.m. to 7 p.m.

 

PEDESTRIAN ACCESS located on the west side of Hamner Avenue from Schleisman Road to the southern crosswalk at Citrus Street. NO pedestrian access across the bridge, please use RTA route 3. 

 

TRAFFIC CHANGE through October 

Hamner Avenue at Citrus Street, crews are working on roadway widening activities. 

REDUCE SPEED and watch for crews working on the shoulder.

 