Week of August 19 - 23 Mission Lakes, Little Morongo, Langlois Resurfacing Projects UPDATE
We completed the improvements to Mission Lakes Blvd., Little Morongo Rd., and Langlois Rd. in the Desert Edge area. Crews are scheduled to complete shoulder work, some minor improvements, and clean the project sites. Please continue to use caution, observe construction warning signs, and follow directions from traffic control personnel. Thank you for your patience and understanding.
We completed the replacement of asphalt pavement to Mission Lakes Blvd, Little Morongo Rd, and Langlois Rd. in the Desert Edge area. Crews are scheduled to work on other improvements along the shoulder, traffic stripe, pavement markings, and roadside signs. Please continue to use caution, observe construction warning signs, and follow directions from traffic control personnel. Thank you for your patience and understanding.
We completed the replacement of asphalt pavement to Mission Lakes Blvd., Little Morongo Rd., and Langlois Rd. in the Desert Edge area . Crews are scheduled to work on shoulder and utility adjustment on the roadway. Please continue to use caution, observe construction warning signs, and follow directions from traffic control personnel. Thank you for your patience and understanding.
We started the replacement of asphalt pavement including concrete dip crossing, cross-gutter, and curb & gutter on Mission Lakes Blvd, Little Morongo Road, and Langlois Road in the Desert Edge area. Estimated completion is October 2024. Crews will "CLOSED TO THRU TRAFFIC" a section of Mission Lakes Blvd. from Warwick Drive to Little Morongo Road. Please follow detour signage from Monday 7/22 to Monday 7/29. Please use caution, observe construction warning signs, and follow directions from traffic control personnel. Thank you for your patience and understanding.