Mecca Neighborhood Construction Notice - July 14-18, 2025

🚧🌳 Construction Update: Mecca Neighborhood Park & Greening Project 🌳🚧

From July 14–18, crews will continue building sidewalks, curbs, gutters, and installing irrigation systems throughout the project area.

✅ Work hours: Monday–Friday, 5:00 AM–5:30 PM
✅ All roadway lanes remain open, but shoulder lanes may be closed.

Please drive carefully through the work zones and allow extra time when traveling. Thank you for your patience as we enhance your community!

📞 More info: rcprojects.org/mecca-neighborhood-park-and-greening

Mecca Neighborhood Park & Greening Project, Construction Notice

🚧🌳 Construction Update: Mecca Neighborhood Park & Greening Project 🌳🚧

From July 7–11, 2025, crews will continue work on sidewalks, curbs, gutters, and irrigation along 66th Avenue and throughout the new park area.

✅ All roadway lanes remain open — but expect shoulder closures and construction activity.
✅ Work hours: Monday–Friday, 5:00 AM – 5:30 PM.

Thank you for your patience as we enhance and green your community!

📞 Questions? Call 760-919-5114
📧 Email: vbarrientos@dccm.com
🌐 Learn more: rcprojects.org/mecca-neighborhood-park-and-greening

 
 
 
Mecca Park & Greening Project - Weekly Status

We started the construction of Community of Mecca Park and Greening (planting trees) on 16 June 2025. The project is to plant about 175 new trees including associated irrigation system and to construct new proposed park at the corner of 2nd Ave, Hammond Rd. and 66th Ave. in the Community of Mecca. Estimated completion in September 2025 (with 90 days monitoring new plants). Please observe construction warning signs and use caution while travelling through the area. Thank you for your patience and understanding.


Note: Due to heat in this region, the contractor is authorized to start the workday at 5:00 AM.