We are continuing to work on roadway widening, new proposed sidewalk, and drainage system improvements on various streets in the Carver Tract Community. Crews are working on drainage systems and concrete curb & gutter. Please observe construction warning signs and use caution while travelling through. Thank you for your patience and understanding. For more information on this project, please visit the project webpage by clicking here.
We are working on roadway widening, new proposed sidewalk, and drainage system improvements on various streets in the Carver Tract Community. Anticipated to complete the project in July/August 2025. Please observe construction warning signs and use caution while travelling through. Thank you for your patience and understanding.
Carver Tract Sidewalk Project Construction Notice, February 18-21, 2025
We completed sidewalk construction and drainage improvements in the Carver Tract area. The contractor is installing pavement markings, doing minor work and clean up, then moving out soon. Please continue to use caution while travelling through the work zone.
The contractor completed most of the underground work for the proposed Storm Water Underground Detention Basin on Luzon Street. Please continue to use caution while travelling though the work zone. We appreciate your cooperation and understanding during the construction.
Multiple underground detention basins continue to be installed on Luzon Street in the Carver Tract area. Please use caution while traveling through the area. For more information regarding this project, please visit the Carver Tract webpage.
We are working on the installation of multiple underground detention basins on Luzon Street in the Carver Tract area. Please observe “ROAD CLOSED” area and use caution while travelling through the area. Thank you for your patience and understanding.
The contractor is working on proposed underground storm water detention basin in the Carver Tract area. Please do not enter the construction area.
Construction of the Carver Tract Sidewalk & Drainage improvements resumed on September 14, 2022. The contractor closed Luzon Street from 48th Avenue to Lingayan Avenue for the construction of an underground storm drain detention system. Please use detour routes.
We completed the proposed sidewalk, surface drainage structures, roadside signs, and fences & gates adjustment in the Carver Tract area. Contractor is waiting for material to construct a underground storm water detention basin on Luzon Street. Tentative schedule for this work is in July 2022.
We completed all concrete curb & gutter and sidewalk in the Carver Tract area. The contractor is working on adjusting affected fences, gates, and other facilities. We are experiencing a delay with material for underground storm drain detention system. The contractor will clean and secure the project site prior to stop the construction. Please use caution while driving/walking through the area. Construction NOTICE (pdf)