Carver Track Phase 2 Construction Notice - April 14-18, 2025
Crews will continue to construct sidewalks.
Crews will grade and subgrade for the new curb and gutter on Leyte Ave and Luzon St.
Crews continue to construct driveways on select properties.
LANE RESTRICTIONS:
Expect to see lane restrictions. Drive slowly and look for cones or other traffic control devices that will keep work areas separate from traffic.
We are continue working on roadway widening, new proposed sidewalk, and drainage system improvements on various streets in the Carver Tract Community. Crews are working on concrete curb & gutter and sidewalk to various streets in the community. Please observe construction warning signs and use caution while travelling through. Thank you for your patience and understanding.
We are continuing work on roadway widening, new proposed sidewalk, and drainage system improvements on various streets in the Carver Tract Community. Crews are working on drainage systems and concrete curb & gutter. Please observe construction warning signs and use caution while travelling through. Thank you for your patience and understanding.
We are continuing to work on roadway widening, new proposed sidewalk, and drainage system improvements on various streets in the Carver Tract Community. Crews are working on drainage systems and concrete curb & gutter. Please observe construction warning signs and use caution while travelling through. Thank you for your patience and understanding. For more information on this project, please visit the project webpage by clicking here.
We are working on roadway widening, new proposed sidewalk, and drainage system improvements on various streets in the Carver Tract Community. Anticipated to complete the project in July/August 2025. Please observe construction warning signs and use caution while travelling through. Thank you for your patience and understanding.
Carver Tract Sidewalk Project Construction Notice, February 18-21, 2025
We completed sidewalk construction and drainage improvements in the Carver Tract area. The contractor is installing pavement markings, doing minor work and clean up, then moving out soon. Please continue to use caution while travelling through the work zone.
The contractor completed most of the underground work for the proposed Storm Water Underground Detention Basin on Luzon Street. Please continue to use caution while travelling though the work zone. We appreciate your cooperation and understanding during the construction.
Multiple underground detention basins continue to be installed on Luzon Street in the Carver Tract area. Please use caution while traveling through the area. For more information regarding this project, please visit the Carver Tract webpage.