Lincoln Street Construction Completed

Lincoln Street

 

Thank you for your patience during construction. 

Construction completed January 26, 2023.

 

RivCoTrans ConnectingCommunities

Steven Graylincoln
Lincoln Street Weekly Update- Week of 1/16/22

We completed the removal & replacing of existing pavement with new asphalt on Lincoln Street from Indiana Avenue to Magnolia Avenue in the Home Gardens area. The contractor is working on traffic stripe, adjusting manholes to grades, and traffic signal detection system this week. Please use caution and observe warning signs while travelling through the work zone. Thank you for your understanding.

Yvette Munozlincoln
LINCOLN STREET UPDATE Week of Dec. 12th

LINCOLN STREET UPDATE from Indiana Avenue to Magnolia Avenue in the Home Gardens area. Due to contractor’s conflicting work schedule, the contractor is scheduled to remove existing asphalt pavement and pave new asphalt starting Today December 12, 2022. The road surface around all new concrete cross gutters and curb ramps are rough/uneven. Please use caution and observe warning signs while travelling through the work zone.

Steven Graylincoln
Lincoln Street Construction to begin October 17th

LINCOLN STREET CONSTRUCTION

To begin the week of October 17, 2022

The County of Riverside Transportation Department will rehabilitate Lincoln Street from Magnolia Avenue to Indiana Avenue. The project will last approximately 8 weeks.

Yvette Munozlincoln