Stetson Ave update

The contractor is scheduled to perform some minor work to correct discrepancies and install Reflective Pavement Markers. Please slow down and observe construction warning signs when workers are working on the road. Thank you!

Stetson Avenue Resurfacing - Weekly Status

Stetson Avenue Resurfacing - Weekly Status

We are nearly completed with the reconstruction of Stetson Avenue from Hemet Street to Santa Fe Street in East Hemet. The contractor is scheduled to perform shoulder work, complete traffic striping, add roadside signs, and other minor work. Please continue to use caution, observe construction warning signs, and expect delays while travelling through the area. Thank you for your understanding and patience.

#EastHemet

#StetsonAveProject

WEEK OF MAY 15

Crews continue to work from 7 a.m. to 6 p.m.

Please drive with caution and reduce your speed.

Stetson Avenue Resurfacing - Weekly Status

The contractor completed the replacement of existing asphalt pavement including driveway tie-in and AC Dikes on Stetson Avenue from Hemet Street to Santa Fe Street in the East Hemet. We are working on new traffic stripe, roadside signs, manholes adjustment, and other minor work. Please continue to use caution, observe construction warning signs, and expect delays while travelling through the area. Thank you for your understanding and patience.

Stetson Ave project work continues

The contractor is scheduled to complete the replacement of existing asphalt pavement on Stetson Avenue from Hemet Street to Santa Fe Street in the East Hemet area this Monday 5/1/23. We are working on new traffic stripe, manhole adjustments, asphalt dike, and other minor work. Please continue to use caution, observe construction warning signs, and expect delays while traveling through the area. Thank you for your understanding and patience.

#EastHemet

#StetsonAveProject

Crews continue paving work today, Friday, April 28 and Monday, May 1 from 7 a.m. to 6 p.m.

Expect delays and please use Johnston Avenue as an alternate route.

Friday: from Madison Ct. to near San Jacinto St.

Monday: from San Jacinto St. to Santa Fe St. (end of project limit

Work continues in East Hemet


#EastHemet

#StetsonAveProject 

#GirardStProject

RAMONA BOWL EVENT:

From E. Florida Ave. PLEASE USE San Jacinto St. to Stetson Ave. to Girard St. 

OR Stetson Ave. to Girard St.

Crews continue to work on pavement improvements in the area.

Monday - Friday and possibly Saturday 7 a.m. - 6 p.m.

Stetson & Girard project update

#EastHemet

Check out the latest...

for the #StetsonAveProject and the #GirardStProject.

Crews continue to work on pavement improvements, Monday - Friday and possible Saturdays 7 a.m. - 4 p.m.


Stetson Avenue Resurfacing - Weekly Status 4/10/23

The contractor is continuing with replacing the existing asphalt pavement on Stetson Avenue from Santa Fe Street to Hemet Street in the East Hemet area. The construction progress is moving as planned. Please use caution, observe construction warning signs, and expect delays while travelling through the area. Thank you for your understanding and patience.

Communities of East Hemet & Valle Vista Construction Update, Week of March 27

East Hemet & Valle Vista:

WEEK OF MARCH 27

Please watch for traffic control operations.

#GirardStProject

Girard St. Project

Monday - Friday & possibly Saturdays

7 a.m. - 6 p.m.

WATCH FOR TRAFFIC CONTROL, one lane may be available.

USE alternate routes.

WEATHER PERMITTING

rcprojects.org/girardstreet

#AcaciaAveProject

Acacia Ave. Project

Monday - Friday & possibly Saturdays

7 a.m. - 6 p.m.

WATCH FOR ROAD CLOSURE, and parking restrictions.

WEATHER PERMITTING

rcprojects.org/girardstreet

#StetsonAveProject

Stetson Ave. Project

Monday - Friday

7 a.m. - 6 p.m.

EXPECT DELAYS, use alternate routes.

WEATHER PERMITTING

rcprojects.org/stetson-ave-resurfacing

#ConnectingCommunities

#RivCoTrans

www.RCProjects.org