Temescal Canyon Road Widening Update

April 29, 2019 - The contractor is currently working on slope grading, storm drains, utility relocations, and retaining walls along Temescal Canyon Road from Dawson Canyon Rd to Dos Lagos Dr.

Current Construction and Traffic Restrictions
A second water main is being relocated just north of Dawson Canyon Rd. Traffic at this location is being pushed on to the shoulders where temporary pavement has been added, so that crews can work behind concrete barriers in the center of the street.

Various utility and storm drain locations along the street are being worked on and will have traffic flagging operations to allow crews to work on the street at those locations.

Curbs and gutters are being installed at various locations throughout the project area. A retaining wall south of Dos Lagos Dr. is being formed next week.

In early May, Southern California Edison will need to disconnect power for 1 shift so that they can connect the newly constructed power lines into the existing power grid. Please watch for futher updates on exact time for this swich as that work draws closer.