Riverside County Projects
Riverside County Transportation Department

SB1 Projects

Resurfacing Projects

54th Avenue Resurfacing

Limits: Harrison Street to Grapefruit Boulevard

Length: Approximately 1.61 miles

District: 4

Community: Thermal

 

The County of Riverside Transportation Department is proposing to resurface approximately 1.61 miles of 54th Avenue from Harrison Street to Grapefruit Boulevard. 54th Avenue is classified as an Urban Arterial Road in the County of Riverside General Plan. 54th Avenue is a two lane road and currently ranges from 24-62 feet wide. The proposed project will include Cold-In-Place recycling (CIR) the roadway width, and overlaying the (CIR) material with Rubberized Hot Mix Asphalt (RHMA).  

 

Additional improvements include:

·       Reconstruction of road section(s)

·       Construction of some driveways, asphalt concrete dike, curb/gutter, and ADA compliant curb ramps

·       Placement of safety edge and shoulder backing

·       Utility adjustments

·       Detector loops

·       Striping of roadway, including pavement markers and reflectors

·       Salvage/removal and installation of new signs

 

No additional right-of-way or temporary construction easements will be required to construct the proposed improvements.

PROJECT SCHEDULE

Environmental Clearance: November 2018

Final Design: July 2018

Construction Start: April 2019

Construction Completion: July 2019

 

FY1819Yvette Munoz