Harrison Street Resurfacing
Limits: 54th Avenue to Airport Boulevard
Length: Approximately 1 Mile
District: 4
Community: Thermal
The County of Riverside Transportation Department proposes to resurface approximately 1 mile of Harrison Street from 54th Avenue to Airport Boulevard. Harrison Street is classified as an Expressway in the County of Riverside General Plan. Harrison Street is a two lane road and currently ranges from 48-58 feet wide. The proposed improvements consist of Cold-in-Place Recycling (CIR) the roadway and overlaying with Rubberized Hot Mix Asphalt (RHMA).
Additional improvements include:
Reconstruction of asphalt concrete driveway
Placement of shoulder backing and safety edge
Detector loops
Striping of roadway, including pavement markers and reflectors
Salvage/removal and installation of new signs
No additional right-of-way or temporary construction easements will be required to construct the proposed improvements. The project improvements will raise the existing roadway profile by 0.17 feet.
PROJECT SCHEDULE
Environmental Clearance: October 2017
Final Design: September 2017
Construction Start: March 2018
Construction Completion: April 2018