Connecting Our Communities

SB1 Projects

Resurfacing Projects

Lovekin Boulevard Resurfacing

Limits: Seeley Avenue to approximately 4,400 feet north of Seeley Avenue
Length: Approximately 4,400 feet
District: 4
Community: River Valley

The County of Riverside Transportation Department is proposing to resurface approximately 4,400 feet of Lovekin Boulevard from Seeley Avenue to approximately 4,400 feet north of Seeley Avenue. Lovekin Boulevard is classified as an Arterial Highway in the County of Riverside’s General Plan. Lovekin Boulevard is a two lane road and currently ranges from 40-52 feet wide with curb along a segment of the roadway. The proposed project will include pulverizing the roadway followed by overlaying with Hot Mix Asphalt (HMA).

Additional improvements include:

  • Reconstruction of asphalt concrete dike and overside drain

  • Reconstruction of concrete curb and ADA deficient curb ramp

  • Construction of asphalt concrete driveway

  • Placement of safety edge

  • Striping of roadway, including pavement markers and reflectors

  • Salvage/removal and installation of new signs

No additional right-of-way will be required to construct the proposed improvements. The project improvements will be within the existing footprint of the roadway and will raise the existing roadway profile by 0.50 feet.

PROJECT SCHEDULE

Environmental Clearance:
September 2020
Final Design: August 2020
Construction Start: November 2020
Construction Completion: January 2021