Mesa Drive Reconstruction
Limits: Bellwood Drive to Black Rock Road/Hobson Way
Length: Approximately 0.25 miles
District: 4
Community: Mesa Verde
The County of Riverside Transportation Department is proposing to reconstruct approximately 0.25 miles of Mesa Drive from Bellwood Drive to Black Rock Road / Hobson Way. Mesa Drive is classified as a Secondary Highway in the County of Riverside’s General Plan. Mesa Drive is a two lane road and currently ranges from 30-84 feet wide with dike along various segments of the roadway. The proposed project will include removing the roadway followed by placing back Hot Mix Asphalt (HMA).
Additional improvements include:
Reconstruction of asphalt concrete dike and overside drain
Reconstruction of concrete curb and ADA deficient curb ramp
Placement of safety edge
Striping of roadway, including pavement markers and reflectors
Salvage/removal and installation of new signs
No additional right-of-way will be required to construct the proposed improvements. The project improvements will be within the existing footprint of the roadway and will not raise the existing roadway profile.
PROJECT SCHEDULE
Environmental Clearance: September 2020
Final Design: August 2020
Construction Start: November 2020
Construction Completion: January 2021