Project Overview
The Riverside County Transportation Department is proposing the construction of a center turn lane (two-way turn lane) along Cajalco Road from Brown Street to Day Street, in Riverside County, California. The proposed project will transition back to the existing cross section to the west of Brown Street and to the east of Day Street. The intersections of Brown Street, Clark Street, and Day Street will be modified to accommodate the improvements. Construction will include new pavement, striping modifications, signing modifications, relocation of electric and transmission electric distribution lines to allow for the improvements, as needed, bus stops at the major intersections, limited Americans with Disabilities Act (ADA) compliant sidewalks at the Clark Street intersection, a new signal at Day Street and the relocation of existing traffic signals at Brown Street and Clark Street. The project is needed to improve safety and traffic operations by eliminating the hazards and inefficiencies of turning movements associated with vehicular traffic on Cajalco Road and intersections of Cajalco Road with Brown Street, Clark Street, and Day Street.
Click here for the Cajalco Widening Project page.
Click here for the Cajalco Resurfacing Project page
project schedule
Environmental Clearance: March 2018
Final Design: June 2019
Obtain Right of Way: June 2019
Project Construction Start: April 2020
☎ Project CONTACT
Scott Staley
(951) 955-2092
cstaley@rivco.org
Project News
Project Impacts
Coordination with future widening project
Prior Rights Determination/ Utility Conflicts
Construction Staging
Maintain traffic flow during construction
Acquire Right of Way
Project Benefits
Improve safety and traffic operations FOR:
Motorists
Residents
Businesses
Emergency Service Providers
Nearby Institutions (e.g. Schools, etc.)
Public Transportation (e.g. Bus Stops)