Slurry Seal FY24-25 District 1, 2, 3 - Weekly Status

• We completed the weed abatement and asphalt repair throughout the project in Districts 1,2 and 3.

• We finished slurry seal in Morgan Hills area. Pavement Marking and first coat of striping has been applied in Morgan Hills area. The contractor will come back to apply second coat of striping latter. All BMPs (sandbags) in the area will be removed after striping process is completed.

• The contractor will continue with crack treatment with crack seal in Riverside area. For slurry seal, the contractor has crew#1 works in the Murrieta and Woodcrest area, crew#2 works in the Perris and Hemet area.

• The contractor has concrete crew work in the Highgrove area to repair/reconstruct curb ramps to comply with ADA standard.

• Please use caution, observe construction warning signs, and follow traffic control staff’s directions while travelling through the work zone. Thank you for your patience and understanding.