Slurry Seal FY24-25 District 4,5, & Lake Cahuilla Veterans Regional Park
• We completed slurry seal in the Lake Cahuilla Veterans Regional Park. Striping in the Park was done.
• The contractor continues examining and marking locations to repair asphalt in Palm Springs and Desert Hot Springs area.
• This week, from Monday 9/30/2024 to Friday 10/4/2024, the contractor will continue to replace speed bumps, car stoppers, and signs in Lake Cahuilla Veterans Regional Park per request form Park’s manager.
• The contractor will begin crack treatment with crack seal in Palm Springs and Desert Hot Springs area.
• Please use caution, observe construction warning signs, and follow traffic control staff’s directions while travelling through the work zone. Thank you for your patience and understanding.