Slurry Seal FY24-25 District 1,2,3 - Weekly Status
Slurry Seal FY24-25 District 1,2,3 - Weekly Status
MAP SCHEDULE (Blue, Yellow, Red)
-Wednesday 10/23 BLUE
Cole Ave
Quarry Cir
Parsons Rd
Mountain Shadow
Wood Rd
-Thursday 10/24 YELLOW
Wood Rd
Cole Ave
Killdeer Ct
Friday 10/25 RED
Markham St
Wood Rd
Eldorado / Elkhorn Rd
Ave C
- We finished repair/upgrade curb ramp throughout the project to meet ADA standard.
- We finished 2 coat striping in Morgan Hills and Murrieta areas.
- The contractor continues to seal crack Temescal Canyon area and touchup works.
- The prime contractor will continue with post sweeping throughout the project
- Striping and Pavement Markings will be installed in Murrieta Hot Springs, Perris and Hemet areas.
- The type I and Type II slurry seal will resume in the Wood Crest area.
- Please use caution, observe construction warning signs, and follow traffic control staff’s directions while travelling through the work zone. Thank you for your patience and understanding.