MAP SCHEDULE

-Monday 10/28 PURPLE
Wood Rd
Markham St
Rocky Summit Dr
Nuthatch St

-Tuesday 10/29 GREEN
Markham St
El Dorado Rd
Ave C / Cole Ave

-Wednesday 10/30 BLUE
Lori Ln
Alice Ln / Dixon Dr
Dixon Dr
Colligan Way / Major Dr
Merriwood
Jaspen Ct
Erwin Ct
Alder / Beachwood / Camphorwood
Central Ave

-Thursday 10/31 YELLOW
Mcdowell
Jepson Ct
Erwin Ct
Erin Dr
Candy Ln
Torrey Pine Ct
Lodgepole Ct
Collegian
Wharton Ct
Syracuse Ct
Academy / University
Howard Manor
Sequoia Ln
Champagne

-Friday 11/1 RED
SCHOLAR CT
SUNSET LANE
LARKSONG ST
VIOLA ST
PRIMROSE LN
TAVA LANE
LADD CT
ONLY CT
TORREY PINE CT
ERIN DR
PARTRIDGE RANCH
BARNHILL
OLD AGENCY RD

- We finished repair/upgrade curb ramp throughout the project to meet ADA standard.

- We finished 2 coats striping in Morgan Hills and Murrieta areas.

- Contractor will continue with the crack seal in the Temescal Canyon area and touch up work.

- The prime contractor will continue with post sweeping throughout the project.

- Striping and Pavement Markings will be installed in Murrieta Hot Springs, Perris, and Hemet areas.

- The type I and Type II slurry seal will resume in the Wood Crest and Hemet area.

- Please use caution, observe construction warning signs, and follow traffic control staff’s directions while travelling through the work zone. Thank you for your patience and understanding.